| Number | Deadline |
|---|---|
|
Q26-21 Humphrey Park Basketball Court Lighting & Electrical Service Improvements
Q26-21 Humphrey Park Basketball Court Lighting & Electrical Service Improvements
The City of Sidney is seeking bids from qualified electrical contractors to furnish all labor, materials, equipment, engineering, permits, inspections, coordination, and incidental items necessary to remove the existing basketball court lighting system and construct a complete new lighting and electrical service installation at Humphrey Park, 600 Buckeye Avenue, Sidney, Ohio.
The Contractor shall provide a separate alternate bid price to furnish all labor and materials for the installation of one (1) 100-watt LED cobra head style night light on one of the newly installed basketball poles.
The project shall be completed on a turnkey basis and shall result in a fully operational lighting system ready for use by the City.
A pre-bid meeting is NOT scheduled. Site visits may be coordinated by contacting Jim Heuing, Parks Dept. Facilities Maintenance Supervisor at 937-498-8155.
The project will require the use of State of Ohio prevailing wage rates for Building Construction ONLY if the bid exceeds the threshold amount of $75,000.
Estimate of Probable Cost: $41,000
| 07/23/2026 03:30 PM UTC |
|
26-20 Sidney Airport New Equipment Hanger
26-20 Sidney Airport New Equipment Hanger
The project is for an approximately 3,900 s.f. one-story, metal building of type IIB construction, group S-1 occupancy. The project involves all site work including asphalt driveways, concrete walks, and lawn seeding; building materials which include but are not limited to concrete foundations and slab, pre-manufactured metal building, hydraulic door, overhead doors, hollow metal doors in hollow metal frames; HVAC units and system; and electrical fixtures and system.
A Non-Mandatory Pre-Bid Meeting will be held onsite at the Sidney City Airport, 14833 Sidney-Plattsville Road, Sidney, Ohio at 9:30 a.m. on Tuesday, July 21, 2026. A walk-through of the site will be offered during the pre-bid meeting.
State of Ohio Prevailing Wage Rates apply.
Estimate: $502,000
| 07/30/2026 03:30 PM UTC |
| Number | Deadline |
|---|---|
|
CDD23-01
Former Wagner Manufacturing Site Building Demolition, Asbestos Abatement, and Site Clearing
ADDENDUM #1 ISSUED MARCH 17, 2023
ADDENDUM #2 ISSUED MARCH 23, 2023
ADDENDUM #3 ISSUED MARCH 24, 2023
ADDENDUM #4 ISSUED APRIL 6, 2023
****An additional site visit will be held March 31, 2023 at 10:00 a.m. EST. This additional site visit is optional and is only for those who attended the mandatory Pre-Bid meeting on March 22, 2023. Those wishing to participate should meet at the site.*****
A MANDATORY PRE-BID CONFERENCE will be held for prospective bidders on March 22, 2023, at 10:00 a.m. (EST) at Council Chambers, City Hall, 201 West Poplar Street, Sidney, Ohio 45365.
The project includes the furnishing of all material; equipment; and labor necessary in the demolition, removal, including asbestos-containing materials (ACM) abatement, and disposal of the existing building on the former Wagner Manufacturing site.
Attention of Bidders is called to all of the requirements contained in the electronic Bid documents, particularly to the Federal Requirements, Federal Labor Standards Provisions and Davis-Bacon Wages, various insurance requirements, various equal opportunity provisions, and requirement for a payment bond and performance bond for 100% of the Contract price.
A Disadvantaged Business Enterprise (DBE) participation goal has not been established for this project; however, DBEs are encouraged to review the project and consider submitting a bid.
Current Federal regulation (23 CFR 635.410) requires all Bidders for Federal or Federal-Aid contracts to submit Bids based upon using only domestic steel and iron products only.
Engineer's Estimate: $3,440,525
| 04/12/2023 07:00 PM UTC |
|
23-05
23-05 2023 Sidewalk Program
The project will consist of the removal and replacement of 4" and 6" concrete sidewalk and drive approaches, replacement of curb, and seeding & mulching.
Construction Estimate: $144,960
| 03/16/2023 03:30 PM UTC |
|
23-04
Echo Drive Extension
The project includes the construction for the extension of Echo Drive to connect with Folkerth Avenue including sanitary sewer & storm sewer.
Attention of Bidders is called to all of the requirements contained in the electronic Bid documents, particularly to the Federal Requirements, Federal Labor Standards Provisions and Davis-Bacon Wages, various insurance requirements, various equal opportunity provisions, and requirement for a payment bond and performance bond for 100% of the Contract price.
A Disadvantaged Business Enterprise (DBE) participation goal has not been established for this project; however, DBEs are encouraged to review the project and consider submitting a bid.
Current Federal regulation (23 CFR 635.410) requires all Bidders for Federal or Federal-Aid contracts to submit Bids based upon using only domestic steel and iron products only.
Engineer's Estimate: $458,104
| 02/23/2023 04:30 PM UTC |
|
23-03
23-03 2023 STREET RESURFACING
The project includes planning of asphalt, placement of asphalt surface course, asphalt concrete surface course, thermoplastic paint markings, and traffic loop.
Construction Estimate: $862,982.60
| 02/16/2023 04:30 PM UTC |
|
23-01
23-01
2023 CURB & GUTTER REPLACEMENT
The project consists of the removal & replacement of curb & gutter and curb ramps with truncated domes and also includes the reconnection of drain tiles and site restoration.
Construction Estimate: $372,653
| 02/02/2023 04:30 PM UTC |
|
23-01
Custenborder Pickleball Courts 2023
The project consists of the construction of four (4) pickleball courts at Custenborder Field including site work, seeding & mulching, installation of 6’ chainlink fence, net posts & netting, and pickleball court surfacing per plan specifications. An alternate bid will be accepted for construction of two (2) additional pickleball courts.
Construction Estimates
Base: $113,892
Alternate: $46,868
| 01/26/2023 04:30 PM UTC |
|
22-21
22-21 Linden Avenue Sanitary Sewer Replacement
The project consists of the replacement of approximately 1,820 l.f. of existing 8” sanitary sewer main on Linden Avenue and Forest Street from Michigan Street to Park Street including 6” sanitary laterals with inspection chambers and sanitary manholes. Also included is site restoration with resurfacing on Linden Avenue.
Construction Estimate: $619,560
| 12/29/2022 04:30 PM UTC |
|
22-20
22-20 Recreational Trail Development Phase V
inclusive of:
COTF-304 Great Miami River Trail
SHEL-005C Great Miami River Recreation Bike Trail
SHEL-006C Sidney Canal Feeder Trail
The project consists of the construction of 3,725 feet of asphalt recreational trail to replace an existing gravel drive. The asphalt trail will pass underneath the I-75 Bridge and tie into the existing asphalt Miami Erie Canal Trail. Two (2) driven steel sheet pile retaining walls will be constructed on the slopes of the I-75 Bridge.
Engineer's Estimate: $1,901,357
| 12/15/2022 04:30 PM UTC |
|
22-18
22-18 Test Drilling, Construction, & Testing of Public Water Supply Wells
The project includes three (3) public water supply wells that are to be drilled and constructed to replace three (3) existing wells (PW-9, PW-10, & PW-7) that have experienced irreversible capacity loss.
A non-mandatory Pre-Bid Meeting will be held at 9:30 a.m. on Monday, November 28, 2022 at the Water Treatment Plant, 880 E. Court Street, Sidney, Ohio. Please RSVP to sepley@sidneyoh.com if you plan to attend the prebid meeting.
Budget Amount: $500,000
| 12/02/2022 08:00 PM UTC |
|
22-19
22-19 Broadway Avenue Water Main Replacement
(Russell Rd to Parkwood St)
OPWC #CM08Z
The project consists of abandoning the existing 8” and 10” cast iron water main and replacing with 10” PVC water main including gate valves, water service branches, fire hydrants, storm and sewer repairs, layout staking, and necessary concrete and pavement removals and restoration.
Engineer's Estimate: $606,776
| 12/01/2022 08:00 PM UTC |
You have successfully created your Digital ID. It has been installed to your browser.
We recommend that you also download a backup of your Digital ID and save it securely to an external storage location, as this file must be installed again if you intend to use a different browser or computer for bidding, document signing, and solicitation management.
Learn more about managing your Digital ID.Click Install Backup ID to use your Digital ID in this location.
If you don't have a copy of your backup ID, but you have access to the computer and browser where it was first created, you can still create a backup ID to install to this location. For help, see how to back up your Digital ID.
If you don't have access to the original computer and browser, you can create a new Digital ID below.