General Info

Business Logo

City of Newark, Ohio

40 West Main Street, Newark, OH 43055
(740) 670-7727


Standard Documents

Name * Description
NewarkStandardConstructionDrawings_July2018.pdf (1.16 MB)
1 Document

Upcoming Solicitations

Number Deadline
0 Solicitations

Closed Solicitations

Number Deadline
2021-18; South Second Street Interceptor Project
A MANDATORY PRE-BID MEETING IS SCHEDULED FOR AUGUST 15TH, 2023, AT 10:00 AM. SEE SECTION 00 10 00 OF THE BID BOOK FOR MORE DETAILS. This Project is located in Newark, Ohio and extends on S. 2nd Street between E. Walnut Street and the South Fork Licking River and on National Drive between S. 4th Street and S. 2nd Street. The Work to be performed includes, but is not limited to, separating combined sewers and constructing new sanitary and storm sewers by means of open-cut, with all associated manholes and appurtenances; replacement and consolidation of potable drinking water piping including all associated valves, hydrants, and appurtenances; replacing streets including curbs, sidewalks, and accessories; pedestrian-friendly features; lighting, and associated components as specified in these contract documents. The Work will include trenchless installation of sanitary sewer pipe underneath the Genesee and Wyoming Railroad. The Work will include the demolition of the existing CSO 1013 structure and construction of a new CSO 1013 structure. The Work will include the demolition of the existing Stop Log Storage Building and construction of a new Stop Log Storage Building. - REVISED PER ADDENDUM NO. 2 Engineer's estimate of probable cost is: $24,122,000 (Base Bid) - REVISED PER ADDENDUM NO. 2 $ 4,256,500 (Alternate Bid) - REVISED PER ADDENDUM NO. 2
09/01/2023 03:00 PM UTC
2023-07; Reddington Park Upgrades - Shelters and Enclosure (ReBid 2)
This project consists of the construction of the following structures and appurtenances: -24'x24' Shelter House -34'x34' Shelter House -10'x14' Porta-Jon Enclosure Architect's estimate of probable cost is $177,000
07/19/2023 04:00 PM UTC
2023-01; Newark Street Resurfacing Project
This project consists of: nearly 100,000 SY of pavement planing, about 10,000 tons of asphalt, almost 5,000 SY of pavement removal, and associated pavement striping. Engineer's estimate of probable cost is $1,600,000.00
06/30/2023 04:00 PM UTC
2021-27; Soldier Pile and Lagging Wall (ReBid)
This project consists of the construction of a soldier pile and timber lagging wall, including all related grading and site work described within the plans. Engineer's estimate of probable cost is $200,000
06/30/2023 04:00 PM UTC
202213 - Eastside Water Transmission Main Project
This project includes approximately 10,500 LF of 16" watermain installation, installed via a combination of open excavation, horizontal directional drilling and jack and bore; Also included is approximately 15,000 SY of chip and seal, 17,000 SY of asphalt overlay and 2,500 SY of asphalt milling. Bids will be opened at noon on Friday, June 23, 2023. The estimated construction cost for the project is $4,401,151.00.
06/23/2023 04:00 PM UTC
202318 - City of Newark, OH Land Application, Beneficial Reuse or Landfill Disposal of Biosolids
The work to be performed under this Contract consists, in general, of furnishing all equipment, personnel, labor, materials, tools, facilities and incidentals necessary to load, haul and reuse/dispose of the biosolids produced at the City of Newark Wastewater Treatment Plant on approved land application sites or landfills.
06/05/2023 04:00 PM UTC
202313 - Lead Water Service Line Replacement Project #3
This Project includes 400 lead and/or galvanized water service lines to be replaced. The work will be located within the City of Newark as depicted on the attached map entitled Lead Service Line #3 Map.
05/09/2023 04:00 PM UTC
2023-07; Reddington Park Upgrades - Shelters and Enclosure (ReBid)
This project consists of the construction of the following structures and appurtenances: -24'x24' Shelter House -34'x34' Shelter House -10'x14' Porta-Jon Enclosure Architect's estimate of probable cost is $177,000
04/19/2023 04:00 PM UTC
2018-22; E. Church St. Enhancement & Alley Rehab (ReBid)
This project consists of: streetscaping of one block of street; including sidewalk, lighting, landscaping, hardscaping, curb & gutter, and minor storm work; along with the reconstruction of 3 alleys. Engineer's estimate of probable cost is $950,000
03/28/2023 04:00 PM UTC
2023-07; Reddington Park Upgrades - Shelters and Enclosure
This project consists of the construction of the following structures and appurtenances: -24'x24' Shelter House -34'x34' Shelter House -10'x14' Porta-Jon Enclosure Architect's estimate of probable cost is $177,000
03/21/2023 04:00 PM UTC
11 - 20 of 48 Solicitations
2 4 5