Number Deadline
CID 2024-370
This work shall consist of furnishing all labor, equipment and material, and in performing all operations necessary for the rejuvenation of and in-depth sealing of asphaltic-concrete surface course by spray application of a cationic rejuvenating agent composed of petroleum oils and resins emulsified with water, complete, in accordance with the specifications and subject to the terms and conditions of the contract. Completion Date: September 1, 2024 Engineer Estimate: $170,191.45
05/17/2024 06:00 PM UTC
1 Solicitation

Closed Solicitations

Number Deadline
CID 2023-103
Project Number: CID 2023-103 Project Name: 2023 Summit County Regional Concrete Pavement Repair Program Project Location: Bath, Copley, Sagamore, Twinsburg Twps. and Village of Lakemore Engineer's Estimate: $661,350.00 Completion Date: September 30, 2023
03/09/2023 07:00 PM UTC
PID 108200
Roadway Minor Rehab – Existing roadway to be widened and overlayed. To Accommodate the proposed widened roadway/shoulders, widening will take place the west side of the roadway. Thereby requiring the crown to be shifted accordingly, a variable depth leveling course will be added to provide a consistent cross slope. Project Length os 0.90 Miles Completion Date; September 30, 2023 Engineer's Estimate: $1,108,207.00
02/09/2023 07:00 PM UTC
PID 113945
SUM-CR 239-01.04 Christman Rd. Bridge over Nimisila Reservoir Replacement of bridge on Christman Road over the Nimisila Reservoir with an entire new structure. Curs/Parapets will be constructed along with a 12-foot-wide future multi-use path (separated by a concrete barrier) on the west side of the bridge. DBE GOAL 10%: Completion Date; September 30, 2023 Engineer's Estimate: $1,352,000.00
01/13/2023 07:00 PM UTC
PID 113152
SUM-CR 137-0.02 Pressler Rd. Bridge over S. Fork of Tuscarawas River Replacement of the two-span concrete slab structure carrying Pressler Road (CR 137) over South Fork Tuscarawas River. The work includes removal of the existing bridge and replacement with a new composite concrete box beam bridge on new foundations. Additional work items include new approach slabs, replacement of roadway approach pavement, rock channel protection, shoulders, and guardrail each side of the bridge, and maintaining traffic DBE GOAL 10%: Completion Date; October 30, 2023 Engineer's Estimate: $944,683.18
12/15/2022 07:00 PM UTC
PID 108453
Akron Cleveland Road Resurfacing (CH 16) Scope of work; Roadway Minor Rehab – Existing roadway to be milled, widened, and overlaid form the City of Cuyahoga Falls north Corporation Limit to the Village of Boston Heights south Corporation Limit. Substandard shoulders will be widened and improved where possible. The existing cross slope will be maintained. Project length is 1.56 miles. DBE GOAL 7%: Completion Date; September 30, 2022 Engineer's Estimate: 1,175,352.45
08/26/2022 06:00 PM UTC
PID 108467 & 108468
DBE GOAL 8%: Cleveland Massillon Rd. Part 1 – The work within the limits of this 1.44 mile resurfacing and shoulder widening improvement project. Work includes planing of existing asphalt concrete wearing course, repair of deteriorated flexible and rigid base, paved shoulder widening (including through the rock-cut section), asphalt overlay and other miscellenous work. Cleveland Massillon Rd. Paart 2 – Existing roadway to be milled and overlayed from 400 feet north of Minor Rd. to the east leg of Ridgewood Rd, omitting the 640-foot portion previously improved at Copley Circle and the Railroad Crossing. Substandard shoulders will be restored and improved where possible. Replacement of existing storm sewers and catch basins along Cleveland-Massillon Rd. and the reconstruction of existing driveways as needed. Project length is 1.81 miles. Completion Date; July 15, 2023 Engineer's Estimate: 2,903,082.29
05/25/2022 06:00 PM UTC
PID 108140 R
Ravenna Road Resurfacing Part 1 DBE GOAL 7%: Description of Job: Existing roadway to be milled, widened, and overlayed from approximately 500 feet north of intersection of Ravenna Rd. with Old Mill Rd. to the City of Twinsburg Limits. Substandard shoulders will be widened and improved where possible. The existing cross slope will be maintained. The existing box culvert 3600 feet north of Old Mill Rd. will be replaced. Project Length of 1.15 Miles Completion Date - June 30, 2023. Engineer's estimate - $1,099,696.53
05/25/2022 06:00 PM UTC
PID 108454 R
Olde 8 Road Resurfacing DBE GOAL 7%: Existing roadway to be milled, widened, and overlaid form the Northfield Center Township southern border to the south end of the intersection return at Highland Rd. Substandard shoulders will be widened and improved where possible. The existing cross slope will be maintained. Olde Eight Road will be widened on the north and south approaches to the intersection with Twinsburg Rd. to add a northbound and southbound left-turn lanes. The existing box culvert 470 feet north of Lighthouse Lane will be extended. Project length is 1.19 miles. Completion Date; June 30, 2023 Engineer's Estimate: 1,259,218.95
05/25/2022 06:00 PM UTC
PID 107797
DBE GOAL 7%: Description of Job: Provide a new pedestrian bridge (CUVA FMSS #249738) connector from the Cuyahoga Valley National Park Visitor Center and trail head located on Boston Mills Rd. east of the Riverview Rd. intersection. Proposed pedestrian bridge will span the Cuyahoga River and extend to an existing parking facility that connects to the Ohio & Erie Towpath Trial. Completion Date: October 30, 2022, Engineer's Estimate: $1,222,873.94
04/29/2022 06:00 PM UTC
PID 108454
Olde 8 Road Resurfacing DBE GOAL 7%: Existing roadway to be milled, widened, and overlaid form the Northfield Center Township southern border to the south end of the intersection return at Highland Rd. Substandard shoulders will be widened and improved where possible. The existing cross slope will be maintained. Olde Eight Road will be widened on the north and south approaches to the intersection with Twinsburg Rd. to add a northbound and southbound left-turn lanes. The existing box culvert 470 feet north of Lighthouse Lane will be extended. Project length is 1.19 miles. Completion Date; September 30, 2022 Engineer's Estimate: 1,094,973.00
04/15/2022 06:00 PM UTC