General Info

Business Logo

Solicitations and notifications are free for this business.

Commonwealth of Massachusetts, Executive Office of Energy & Environmental Affairs, Dept. of Conservation & Recreation

10 Park Plz Suite 6620, Boston, MA 02116-3933
(857) 283-6746

Please note Effective  January 2025 there will be an increase to the SDP requirements.
MBE and WBE  requirements will no longer be combined.

Requirements as followed: 

MBE:   6%
WBE: 10%
VOBE  3%


For our Supplier Diversity Partners : https://www.diversitycertification.mass.gov/BusinessDirectory/BusinessDirectorySearch.aspx

Please note starting in 2024, our bid day deadline will now be Thursday's @ 12:00PM

Standard Documents

Name * Description
SDP Instructions and COP.pdf (475 KB)
SDP Instructions and COP.
1 Document

Upcoming Solicitations

Number Deadline
P26-3665-M4A
Traffic Signal Maintenance - Statewide The project consists of providing on-call maintenance, repair, emergency response, modification, and upgrade services for traffic signal and traffic control systems, as directed by the Engineer. Work shall include preventative maintenance, emergency repairs, knockdown restoration, equipment replacement, and system improvements necessary to maintain proper operation. The estimated project cost is $ 2,500,000.00 The work is to be accomplished within 730 calendar days of notice to proceed. Liquidated damages in the amount of $100.00 per day will be assessed if the work has not been completed in accordance with the provisions of the contract within the time specified (as extended by any authorized extension of time granted in accordance with the contract provisions). Bidders must be pre-qualified by the Massachusetts Dept. of Transportation (MassDOT) Highway Division in TRAFFIC SIGNALS to bid on the above project. An award will not be made to a Contractor who is not pre-qualified by MassDOT prior to the opening of Proposals. The Proposed contract includes a requirement of 6% for MBE (Minority Business Enterprise) 10% for WBE (Women Business Enterprise) and 3% VOBE requirement (Veteran-Owned Business Enterprise). The applicable local minority workforce utilization percentage is a minimum goal of 15.3%. The applicable local women workforce utilization percentage is a minimum goal of 6.9%. Each bid must be accompanied by a bid deposit, in the form of a bid bond, cash, certified check, or a treasurer's or cashier's check issued by a responsible bank or trust company, payable to the Department of Conservation and Recreation in the amount of 5% of the bid. Each bid must be submitted through DCR’s E-Bid room at www.bidexpress.com/businesses/36765/home. Please ensure that your bid is complete and marked as responsive when submitting through DCR’s Bid room. Any bids found to be incomplete and/or marked unresponsive will be rejected by DCR and will not be considered when awarding the project. Bids are subject to the provisions of M.G.L. Ch. 30, Sect. 39F, G, H and M inclusive. Wages are subject to minimum wage rates as per M.G.L. Ch. 149, sections 26 to 27D inclusive. The Department reserves the right to waive any informalities in or to reject any and all bids if it be in the public interest to do so. Nicole LaChapelle, Commissioner Massachusetts Department of Conservation and Recreation
05/21/2026 04:00 PM UTC
W26-7610-C01
Sub Rebid Quabbin Reservoir Generator Replacement Project Site #1 - 485 Ware Road, Belchertown, Massachusetts 01007 County: Hampshire Site #2 – Quabbin Hill Road, Ware, Massachusetts 01082 County: Hampshire Sub-BID proposals shall be submitted on a form furnished by the Department and will be received until 12:00 PM on Thursday, May 21, 2026 for the following FILED SUB- BIDS: (1) Electrical will be received through DCR’s E-bid room www.bidexpress.com/businesses/36765/home The project proposes the replacement of two (2) emergency generators for DCR Quabbin Reservoir facilities located in Belchertown and Ware, Massachusetts. The project will result in the removal and installation of two new generator units complete with upgraded automatic transfer switches, remote monitoring systems and fuel storage systems. The project consists of electrical and site modifications as indicated on the drawings. The project is being funded in part with funding approved by the Federal Emergency Management Agency (FEMA). Total construction costs are estimated at: $ 442,420.00 The work is to be accomplished within 270 calendar days of a notice to proceed. Liquidated damages in the amount of $ 500.00 per day will be assessed if the work has not been completed in accordance with the provisions of the contract within the time specified (as extended by any authorized extension of time granted in accordance with the contract provisions). The proposed contract includes a requirement of 6% of the bid price for minority-owned business enterprises and a requirement of 10% for women-owned business enterprises. The applicable local minority workforce utilization percentage is a minimum requirement of 15.3%. The applicable local women workforce utilization percentage is a minimum requirement of 6.9%. The Commonwealth requires participation of Veteran-Owned Business Enterprises (“VOBE”) on its construction projects. The Veteran-Owned Business Enterprise benchmark for this contract is 3.0%. Each bid must be accompanied by a bid deposit, payable to the Department of Conservation and Recreation in the amount of 5% of the bid. Bid Bonds must be submitted electronically, please ensure your company and your bonding agent's company register with one of the Bid Bond agencies affiliated with Bid Express: If you need additional assistance, please call the Bid Express Customer Support Team at 888-352-2439, available Monday - Friday from 7:00am – 8:00pm (EDT). You can also email the team support@bidexpress.com or refer to the Vendor Resource page Bids are subject to the provisions of M.G.L. Ch. 149, sections 44A to H, inclusive. In addition, bids are also subject to Ch. 30, Sect. 39F, G, H and M inclusive. Wages are subject to minimum wage rates as per Mass. Gen. L. Ch. 149, sections 26 to 27D inclusive. The Department reserves the right to waive any informalities in or to reject any and all bids if it be in the public interest to do so. All Bidders for this project are required to be certified with the Massachusetts Division of Capital Asset Management and Maintenance (DCAMM) and must submit with the bid an update of their respective qualifications. General bidders must be certified in Mechanical Systems or Prime Electrical. Nicole LaChapelle Massachusetts Department of Conservation and Recreation  
05/21/2026 04:00 PM UTC
P26-3633-C2A
Toohig Playground Site Improvements 630 Gallivan Boulevard, Dorchester, MA This project consists of rehabilitation an existing park and playground including demolition of existing pavements, surfacing and playground equipment; construction of new concrete and bituminous concrete pavements; re-paving existing bituminous concrete pavements; installation of new playground and fitness equipment (supplied by the DCR), poured-in-place rubber safety surfacing, basketball hoops and nets, fencing, and concrete edging; and installation of new dugout shade structures, team benches, benches, bicycle parking, trash receptacles, water fountain, loam, new lawn, and new trees. The estimated project cost is $1,000,000.00 The work is to be accomplished within 150 calendar days of a notice to proceed. Liquidated damages in the amount of $1,000.00 per day will be assessed if the work has not been completed in accordance with the provisions of the contract within the time specified (as extended by any authorized extension of time granted in accordance with the contract provisions). Bidders must be pre-qualified by the Massachusetts Dept. of Transportation (MassDOT) Highway Division in Recreational Facilities to bid on the above project. An award will not be made to a Contractor who is not pre-qualified by MassDOT prior to the opening of Proposals. The Proposed contract includes a requirement of 6% for MBE (Minority Business Enterprise) 10% for WBE (Women Business Enterprise) and 3% VOBE requirement (Veteran-Owned Business Enterprise). The applicable local minority workforce utilization percentage is a minimum goal of 15.3%. The applicable local women workforce utilization percentage is a minimum goal of 6.9%. Each bid must be accompanied by a bid deposit, in the form of a bid bond, cash, certified check, or a treasurer's or cashier's check issued by a responsible bank or trust company, payable to the Department of Conservation and Recreation in the amount of 5% of the bid. Each bid must be submitted through DCR’s E-Bid room at www.bidexpress.com/businesses/36765/home. Please ensure that your bid is complete and marked as responsive when submitting through DCR’s Bid room. Any bids found to be incomplete and/or marked unresponsive will be rejected by DCR and will not be considered when awarding the project. Bids are subject to the provisions of M.G.L. Ch. 30, Sect. 39F, G, H and M inclusive. Wages are subject to minimum wage rates as per M.G.L. Ch. 149, sections 26 to 27D inclusive. The Department reserves the right to waive any informalities in or to reject any and all bids if it be in the public interest to do so. Nicole LaChapelle, Commissioner Massachusetts Department of Conservation and Recreation
06/11/2026 04:00 PM UTC
W26-7610-C01
Rebid General: Quabbin Reservoir Generator Replacement Project Site #1 - 485 Ware Road, Belchertown, Massachusetts 01007 County: Hampshire Site #2 – Quabbin Hill Road, Ware, Massachusetts 01082 County: Hampshire The project proposes the replacement of two (2) emergency generators for DCR Quabbin Reservoir facilities located in Belchertown and Ware, Massachusetts. The project will result in the removal and installation of two new generator units complete with upgraded automatic transfer switches, remote monitoring systems and fuel storage systems. The project consists of electrical and site modifications as indicated on the drawings. The project is being funded in part with funding approved by the Federal Emergency Management Agency (FEMA). Total construction costs are estimated at: $ 442,420.00 The work is to be accomplished within 270 calendar days of a notice to proceed. Liquidated damages in the amount of $ 500.00 per day will be assessed if the work has not been completed in accordance with the provisions of the contract within the time specified (as extended by any authorized extension of time granted in accordance with the contract provisions). The proposed contract includes a requirement of 6% of the bid price for minority-owned business enterprises and a requirement of 10% for women-owned business enterprises. The applicable local minority workforce utilization percentage is a minimum requirement of 15.3%. The applicable local women workforce utilization percentage is a minimum requirement of 6.9%. The Commonwealth requires participation of Veteran-Owned Business Enterprises (“VOBE”) on its construction projects. The Veteran-Owned Business Enterprise benchmark for this contract is 3.0%. Each bid must be accompanied by a bid deposit, payable to the Department of Conservation and Recreation in the amount of 5% of the bid. Bid Bonds must be submitted electronically, please ensure your company and your bonding agent's company register with one of the Bid Bond agencies affiliated with Bid Express: If you need additional assistance, please call the Bid Express Customer Support Team at 888-352-2439, available Monday - Friday from 7:00am – 8:00pm (EDT). You can also email the team support@bidexpress.com or refer to the Vendor Resource page Bids are subject to the provisions of M.G.L. Ch. 149, sections 44A to H, inclusive. In addition, bids are also subject to Ch. 30, Sect. 39F, G, H and M inclusive. Wages are subject to minimum wage rates as per Mass. Gen. L. Ch. 149, sections 26 to 27D inclusive. The Department reserves the right to waive any informalities in or to reject any and all bids if it be in the public interest to do so. All Bidders for this project are required to be certified with the Massachusetts Division of Capital Asset Management and Maintenance (DCAMM) and must submit with the bid an update of their respective qualifications. General bidders must be certified in Mechanical Systems or Prime Electrical. Nicole LaChapelle Massachusetts Department of Conservation and Recreation  
06/11/2026 04:00 PM UTC
4 Solicitations

Closed Solicitations

Number Deadline
P21-3409-C1A
Intersection Improvement Project – Fresh Pond Parkway at Mt. Auburn Street The project consists of, but is not be limited to, installation of new traffic signal equipment, geometric roadway modifications, narrowing Fresh Pond Parkway southbound barrel, from Brattle Street to Mt. Auburn Street, and Gerry’s Landing Road southbound barrel, from Mt. Auburn Street to Memorial Drive, to two lanes from three, pavement milling and overlay, installation of new curb and raised median to separate the proposed two-way bicycle path – on Gerry’s Landing Road southbound, starting south of Mt. Auburn Street intersection and ending at Memorial Drive intersection – from vehicular traffic. The estimated project cost is $1,780,000.00 CONTRACTS FOR PUBLIC WORKS PROJECTS AND FOR BUILDING PROJECTS ESTIMATED TO COST MORE THAN $25,000 BUT NOT MORE THAN $100,000 SUBJECT TO THE PROVISIONS OF M.G.L. CH. 30 SEC. 39M
12/23/2020 04:00 PM UTC
P21-3409-M2A
Servicing of High Voltage Power Line Systems. The estimated project cost is $ 1,000,000.00 CONTRACTS FOR PUBLIC WORKS PROJECTS AND FOR BUILDING PROJECTS ESTIMATED TO COST MORE THAN $25,000 BUT NOT MORE THAN $100,000 SUBJECT TO THE PROVISIONS OF M.G.L. CH. 30 SEC. 39M
12/16/2020 04:00 PM UTC
P18-3192-C2A
Contract No:P18-3192-C2A: Beartown Superintendent’s House Structural Repair The estimated project cost is $213,157.00
12/16/2020 04:00 PM UTC
P09-2580-C2A
Sub-Bids :ISLAND DISTRICT HEADQUARTERS BUILDING EXTERIOR RENOVATIONS: Sub-BID :Electrical; HVAC; Masonry; Metal Windows; Painting; Waterproofing, Damp proofing and Caulking.
12/16/2020 04:00 PM UTC
P18-3234-C1A
CAPE COD RAIL TRAIL EXTENSION WELLFLEET, MA The estimated project cost is $ 2,068,196. CONTRACTS FOR PUBLIC WORKS PROJECTS AND FOR BUILDING PROJECTS ESTIMATED TO COST MORE THAN $25,000 BUT NOT MORE THAN $100,000 SUBJECT TO THE PROVISIONS OF M.G.L. CH. 30 SEC. 39M
12/09/2020 04:00 PM UTC
P20-3354-C5A
Carpentry at DCR Facilities: Western & Central & Massachusetts Counties: Berkshire, Franklin, Hampshire Hamden,Worcester Estimate $ 700,000
11/25/2020 04:00 PM UTC
P20-3354-C4A
Carpentry at DCR Facilities - Eastern Massachusetts Essex ,Middlesex ,Suffolk ,Norfolk Worcester,Plymouth ,Bristol ,Barnstable The estimated project cost is $ 1,300,000
11/25/2020 04:00 PM UTC
P20-3341-M01 Catch Basin & Drainage Infrastructure Cleaning and CCTV Inspection
Catch Basin & Drainage Infrastructure Cleaning and CCTV Inspection Statewide The project consists of cleaning and/or investigation of DCR drainage infrastructure. Typically, work shall include, during regular and emergency response times, the cleaning of catch basin and manhole structures with a vacuum truck, high pressure water jetting of drainage lines, and CCTV investigation. This project shall also include the removal and disposal of all sediments in compliance with the regulations of the Department of Environmental Protection in effect at the time of disposal. CONTRACTS FOR PUBLIC WORKS PROJECTS AND FOR BUILDING PROJECTS ESTIMATED TO COST MORE THAN $25,000 BUT NOT MORE THAN $100,000 SUBJECT TO THE PROVISIONS OF M.G.L. CH. 30 SEC. 39M
10/28/2020 03:00 PM UTC
P20-3351-C3A Fire Alarm System at John Augustus Hall
Installation of a new fire alarm system including; all labor, electrical work, necessary equipment and materials. Demolition of existing non-functioning system, and testing of new system. The estimated project cost is $315,000 CONTRACTS FOR BUILDING PROJECTS ESTIMATED TO COST OVER $100,000 SUBJECT TO THE PROVISIONS OF M.G.L. C. 149
10/22/2020 03:00 PM UTC
P20-3361-C5A: Painting and Minor Repairs to the Arthur Fiedler Footbridge over Storrow Drive
The project consists of concrete repairs to the bridge spans, approach ramps/abutments, installation of new expansion joints, application of concrete coating (including surface preparation and crack/joint treatments), and steel painting of columns (including surface preparation). Alternate 1 includes preparation and installation of anti-skid waterproofing on the bridge deck and approach ramp surfaces The estimated project cost is $ 890,000.00 CONTRACTS FOR PUBLIC WORKS PROJECTS AND FOR BUILDING PROJECTS ESTIMATED TO COST MORE THAN $25,000 BUT NOT MORE THAN $100,000 SUBJECT TO THE PROVISIONS OF M.G.L. CH. 30 SEC. 39M
09/28/2020 03:00 PM UTC
291 - 300 of 315 Solicitations