The Milwaukee Department of Public Works has the greatest impact of any city department on daily life in Milwaukee.

We are responsible for the design, maintenance, and operation of streets, sidewalks, alleys, bridges, sewers, water mains, underground conduit, telecommunications services, traffic signals, and street lighting for the City of Milwaukee that covers more than 95 square miles; 221 city buildings, a fleet of over 1,500 vehicles, 476 acres of boulevards and green space, and 200,000 street trees.

Standard Documents

Name * Description
0 Documents

Upcoming Solicitations

Number Deadline
OFFICIAL NOTICE 73-1-2026
The general work requested is: 8” CONCRETE PAVEMENT, 8” CONCRETE PAVEMENT WITH INTEGRAL CURB, VARIABLE THICKNESS ASPHALT, CONCRETE CURB AND GUTTER, CONCRETE WALK, 7” CONCRETE DRIVEWAY, BASE AGGREGATE, CONCRETE TRAFFIC ISLANDS, ROADWAY FILLING, CATCH BASINS, STORM WATER DRAINS, PAVEMENT REMOVAL, ROADWAY CUTTING, CURB AND GUTTER REMOVAL, CONCRETE SIDEWALK REMOVAL, SAWCUTTING, CATCH BASIN ABANDONMENT, SIGNAGE AND PAVEMENT MARKING REMOVAL, EPOXY AND COLD PLASTIC PAVEMENT MARKING, LIGHTING INSTALLATION, AND OTHER SITE RESTORATION, ETC. Located at: TD06884511 E. Pittsburg Av.- S. Water St. to S. 1st St. (TID 68) TD05684709 E. Menomonee St. - N. Jefferson St. to N. Milwaukee St. (TID 56) TD05684715 Kinnickinnic River Trail Connections (TID 56)
08/11/2026 03:30 PM UTC
OFFICIAL NOTICE 74-1-2026
The general work requested is: CONSTRUCTION OF 7” CONCRETE ALLEY PAVEMENT, VARIABLE THICKNESS ASPHALTIC CONCRETE PAVEMENT, 7” CONCRETE DRIVEWAY, CONCRETE CURB AND GUTTER, VARIABLE THICKNESS CONCRETE WALK AND/OR CONCRETE DRIVEWAYS, VARIABLE THICKNESS CRUSHED STONE BASE, PERMEABLE PAVERS, SEALING PAVEMENT JOINTS AND CRACKS, STONE BEDDING, SLURRY BACKFILL, CONCRETE AND OTHER REMOVALS, SEWER WORK, ETC.; Located at the following Alleys Bounded by (ABB): ST212160107 E. Bradford Ave., N. Prospect Ave., N. Stowell Ave., E. Webster Pl. ST212220116 W. Hopkins St., W. Townsend St., N. 22nd St., N. 23rd St. ST212220107 W. Greenfield Ave., W. Orchard St., S. 22nd St., S. 23rd St. ST212220118 W. Fond du Lac Ave., W. Meinecke St., W. Wright St., N. 22nd St., N. 23rd
08/12/2026 03:30 PM UTC
OFFICIAL NOTICE 75-1-2026
The general work requested is: CONSTRUCTION OF 7” CONCRETE ALLEY PAVEMENT, VARIABLE THICKNESS ASPHALTIC CONCRETE PAVEMENT, 7” CONCRETE DRIVEWAY, CONCRETE CURB AND GUTTER, VARIABLE THICKNESS CONCRETE WALK AND/OR CONCRETE DRIVEWAYS, VARIABLE THICKNESS CRUSHED STONE BASE, PERMEABLE PAVERS, SEALING PAVEMENT JOINTS AND CRACKS, STONE BEDDING, SLURRY BACKFILL, CONCRETE AND OTHER REMOVALS, SEWER WORK, ETC.; Located at the following Alleys Bounded by (ABB): ST212240109 W. Fiebrantz Ave., W. Hope Ave., N. 62nd St., N. 63rd St. ST212240104 W. Keefe Ave., W. Townsend St., N. 46th St., N. 47th St. ST212240102 W. Appleton Ave., W. Chapman Pl., W. Nash St., W. Potomac Ave.
08/13/2026 03:30 PM UTC
OFFICIAL NOTICE 77-1-2026
60 HYDRANT ALTERATIONS, by qualified City of Milwaukee licensed and bonded contractors. Hydrant alterations will be at scattered locations throughout the Milwaukee Water Works Service area. Hydrant alterations may include, but are not limited to, the procurement of all permits, excavation, traffic control, erosion control, saw-cutting, removal of existing hydrant, restraint of existing hydrant branch, installation of new hydrant assembly, backfilling of the excavation(s), restoration of pavement, curb and gutter, and walk, and final cleanup of the work site. Aggregate slurry backfill shall be required for all excavations. Aggregate slurry backfill shall be as specified in 4.6.6 of the Water Main Installation Specifications. In paved areas, the slurry must be placed to the pavement subgrade. In grass areas, slurry must be placed to 6” below the finished grade and topsoil must be placed to the surface. Includes any necessary hydroexcavation. Temporary and permanent restoration requirements will be at the discretion of MWW. All work shall be in compliance with the City of Milwaukee Rules and Regulations Governing Water Service, the City of Milwaukee Water Service Piping Specifications, and the City of Milwaukee Special Provisions for Lead Service Line Replacement. Prices from all bidders will be kept on file. If the successful bidder fails to fulfill the contract requirements, an agreement with a secondary contractor may be pursued for work at specific emergency locations.
08/19/2026 03:30 PM UTC
OFFICIAL NOTICE 38-1-2026
This project consists of dismantling the processing equipment from the tip floor and processing floor within a fire damaged building. The building and equipment have fire damage throughout. Any hazardous material will need to be removed and disposed of according to state and federal regulations. All furniture must be removed and disposed of and the entire space swept free of debris.
08/21/2026 03:30 PM UTC
5 Solicitations

Closed Solicitations

Number Deadline
OFFICIAL NOTICE 116-1-2024
The general work requested is: CONSTRUCTION STAKING ELECTRICAL INSTALLATION, REMOVAL OF EXISTING LIGHTING UNITS AND INSTALLATION OF NEW LIGHING UNITS PER THE INSTALLATION AND SPECIAL PROVISION GUIDELINES, CONDUIT, ELECTRICAL CABLE, INSTALLATION OF OTHER ELECTRICAL APPURTENANCES, ETC.; RG1515236321/ST240240709 – Street Lighting Series Conversion NM11-12 Area Bounded By (ABB): West Fairmount Avenue, North 51st Street, West Custer Avenue, and North 44th Place
11/22/2024 04:30 PM UTC
OFFICIAL NOTICE 105-1-2024
The general work requested is: CONSTRUCTING BUS BULBS AND PINNED ON MEDIAN ISLANDS ALONG BURLEIGH STREET FROM N. SHERMAN BLVD. TO N. 20TH ST. AND S. CESAR CHAVEZ DRIVE FROM W. MITCHELL ST. TO W. PIERCE ST.
11/15/2024 04:30 PM UTC
OFFICIAL NOTICE 90-1-2024
COMBINED SEWER MAIN RELAY & COMBINED SEWER MAIN LINING & MANHOLE REPAIR AND LINING N. 50th Pl. – W. Vliet St. to 230’ N of W. Galena St. N. 51st St. – W. Vliet St. to W. Vine St. N. 52nd St. – W. Vliet St. to W. Lloyd St. N. 53rd St. – W. Washington Blvd. to W. Vine St. W. Galena St. – N. 49th St. to N. 52nd St. W. Vliet St. – N. 50th St. to N. 53rd St.
11/12/2024 04:30 PM UTC
OFFICIAL NOTICE 119-1-2024
2nd and Plankinton Parking Structure Renovation 2nd and Plankinton parking structure renovation - at east passenger elevator install new water diversion, Alt 1 (expand office, renovate bathroom and demo existing lobby and build new lobby).
11/07/2024 04:30 PM UTC
OFFICIAL NOTICE 103-1-2024
The general work requested is: CONSTRUCTION OF, PROJECT STAKING, VARIABLE THICKNESS ASPHALTIC CONCRETE PAVEMENT, 8” CONCRETE PAVEMENTS, CONCRETE TRAFFIC ISLAND, VARIABLE THICKNESS CONCRETE BASE, CONCRETE CURB AND GUTTER, 5” AND 7” CONCRETE WALKS, INSTALLATION OF CONDUIT, FIBERGLASS/POLYMER CONCRETE PULL BOXES, AND OTHER ELECTRICAL APPURTENANCE, SIGNAGE AND SIGNAGE INSTALLATION, VARIOUS PAVEMENT MARKINGS, CONCRETE REMOVALS, PAVEMENT MARKING, SEWER WORK, WATER WORK, VARIOUS LANDSCAPING AND PLANTING, ETC.: TD05484211 – Burnham Park Traffic Safety Improvements Project @ Various Locations
10/25/2024 03:30 PM UTC
OFFICIAL NOTICE 112-1-2024
C/O Milwaukee Health Department (MHD) – Milwaukee Women’s Center, Indoor Air Quality (IAQ) Upgrades
10/23/2024 03:30 PM UTC
OFFICIAL NOTICE 94-1-2024
The general work requested is: CONSTRUCTION OF, VARIABLE THICKNESS ASPHALTIC CONCRETE PAVEMENT, VARIABLE THICKNESS CONCRETE BASE, 6” CONCRETE BASE, PAVEMENT GRINDING, 7” AND 8” CONCRETE DRIVEWAYS, CONCRETE CURB AND GUTTER, 5” CONCRETE WALKS, PAVEMENT GRINDING, REPAIR PAVEMENT JOINTS AND CRACKS, INSTALLATION OF CONDUIT, FIBERGLASS/POLYMER CONCRETE PULL BOXES, AND OTHER ELECTRICAL APPURTENANCE, GRAVEL FILLING, CONCRETE REMOVALS, PAVEMENT MARKING, SEWER WORK, WATER WORK, TREE CLEARING & GRUBBING, ETC.; ST211050150 – South Robinson Avenue – East Ward Street to East Becher Street
10/22/2024 03:30 PM UTC
OFFICIAL NOTICE 106-1-2024
Milwaukee Police Department – Police Administration Building Service, ATS, & Paralleling Gear Upgrades
10/17/2024 03:30 PM UTC
OFFICIAL NOTICE 111-1-2024
C/O Milwaukee Health Department (MHD) – Salvation Army Emergency Lodge Indoor Air Quality (IAQ) Upgrades
10/16/2024 03:30 PM UTC
OFFICIAL NOTICE 74-1-2024
The general work requested is: CONSTRUCTION OF, 8” CONCRETE PAVEMENT, 8” HIGH EARLY STRENGHT CONCRETE PAVEMENT, VARIABLE THICKNESS CONCRETE BASE, VARIABLE THICKNESS ASPHALTIC CONCRETE PAVEMENT, CONCRETE CURB AND GUTTER, 5” CONCRETE WALKS, DETECTABLE WARNING FIELD, PAVEMENT GRINDING, SEALING PAVEMENT JOINTS AND CRACKS, GRAVEL FILLING, PAVEMENT MARKINGS, SIGNAGE INSTALLATION, CONCRETE REMOVALS, SEWER WORK, WATER WORK, CUC AJUSTMENT, ELECTRICAL CONDUIT INSTALLATION, TREE CLEARING & GRUBBING, TOPSOILING AND SODDING, ETC.; Located at: ST211230124 - North Prospect Avenue – East Knapp Street to East Ivanhoe Place ST211230140 - North Water Street – East Brady Street to North Humboldt Avenue