General Info

Business Logo

University of Northern Iowa

1801 W 31st Street, Cedar Falls, IA 50614-0530
(319) 273-6961


Standard Documents

Name * Description
0 Documents

Upcoming Solicitations

Number Deadline
Commons Window Replacement Phase 1
Remove and dispose of select exterior windows. Install new windows and repair/restore interior finishes and exterior masonry as required. Interior finishes include stone and wood sills, drywall, plaster and tile jambs. Exterior masonry includes brick and limestone masonry.
05/06/2025 07:00 PM UTC
1 Solicitation

Closed Solicitations

Number Deadline
Hagemann Corridor and Lounge Carpet and Paint - Hazardous Material Abatement
Providing asbestos testing and bid documentation for abatement in selected areas of Hagemann Hall. The areas planned for abatement are floors 1-4 in the corridors and student lounges and the basement floor in the student lounge. Competitive bidding of the work and then a construction phase is included in this project.
03/19/2024 07:00 PM UTC
Center for Energy and Environmental Education Window Replacement Phase 6
Replace wood windows in the atrium and on the upper southeast side of the building with fiberglass windows.
03/19/2024 07:00 PM UTC
Nielsen Field House Roof Replacement Phase 2
Removal and replacement of existing EPDM roof and insulation with new fully adhered KEE roof and insulation system. Removal and replacement of flashings, copings, and accessories as required to accommodate full roof replacement. Addition of roof mounted access stairs and guardrail system.
03/07/2024 08:00 PM UTC
Hagemann Corridor and Lounge Carpet and Paint
Replace the carpet and paint in corridors and lounges throughout the building.
03/07/2024 08:00 PM UTC
West Gym Demolition - Hazardous Material Abatement
The removal of all ACM in the building and steam tunnel system. Additional testing will be conducted to verify the locations of ACM.
03/05/2024 08:00 PM UTC
Rod Library VAV Box Replacement Phase 2
Replace existing boxes and lined ductwork with new VAV boxes on the second floor of the library.
11/16/2023 08:00 PM UTC
Maucker Union Ballroom Roof Replacement
As indicated on the project drawings, remove existing rock ballast and EPDM membrane, reuse existing insulation, mechanically attach new insulation into concrete deck, adhere new coverboard and install new adhered Fleecebacked KEE membrane.
11/16/2023 08:00 PM UTC
Noehren Hall Generator Replacement
The project consists of the removal of an existing diesel generator, diesel tank, exhaust piping, and installation of a new natural gas generator, natural gas piping, and exhaust piping.
11/09/2023 08:00 PM UTC
Power Plant Metal Roof Coating
As indicated on the project drawings, clean existing select metal roof areas and conveyor areas, install primer on all areas with rust or corrosion and then install a fluid-applied elastomeric roof coating.
08/10/2023 07:00 PM UTC
Nielsen Field House Roof Replacement Phase 2
Demolition and disposal of existing membrane roofing, insulation and coverboard and select abandoned roof curbs. Patch and repair roof deck. Installation of new insulation (flat and tapered), KEE membrane roofing, fall protection railing and metal flashings and coping.
08/01/2023 07:00 PM UTC
31 - 40 of 138 Solicitations