25-24 PICKLEBALL COURTS
25-24 Pickleball Courts ODNR SHEL-029 2025-0128
The project consists of the construction of two (2) additional pickleball courts at Custenborder Field including site work, seeding & mulching, installation of chainlink fence, net posts & netting, and pickleball court surfacing per plan specifications.
State of Ohio Department of Natural Resources NatureWorks Local Assistance Grant Funds and Capital Improvement Projects funding are being used to assist construction and relevant State requirements will apply.
Domestic steel use requirements as specified in Ohio Revised Code §153.011 apply to this project. Copies of §153.011 can be obtained from any of the offices of the Department of Administrative Services or through http://codes.ohio.gov/orc/153.011.
All contractors and subcontractors involved with the project will, to the extent practicable use Ohio products, materials, services and labor in the implementation of their project. Additionally, contractor compliance with Equal Employment Opportunity requirements is required.
The Contractor shall be required to pay not less than the minimum wage rates established by the Department of Industrial Relations of the State of Ohio.
Engineer's Estimate: $125,501
| 12/04/2025 04:30 PM UTC |
|
25-23 2025 Tree Purchasing & Planting
The project consists of purchasing & planting trees at various public locations within the City of Sidney including all labor, supervision, materials, tools, equipment, machinery, and any/all other necessary and proper items.
BIDDER MUST BE A MEMBER OF THE OHIO GREEN INDUSTRY ASSOCIATION (OGIA); FKA OHIO NURSERY AND LANDSCAPE ASSOCIATION (ONLA). Additional education and experience shall be noted upon Bid submission.
Attention of Bidders is called to all of the requirements contained in the electronic Bid documents, particularly to the Federal Requirements, Federal Labor Standards Provisions and Davis-Bacon Wages, various insurance requirements, various equal opportunity provisions, and requirement for a payment bond and performance bond for 100% of the Contract price.
A Disadvantaged Business Enterprise (DBE) participation goal HAS NOT been established for this project; however, DBEs are encouraged to review the project and consider submitting a bid.
Current Federal regulation (23 CFR 635.410) requires all Bidders for Federal or Federal-Aid contracts to submit Bids based upon using only domestic steel and iron products only.
Estimated Cost: $61,560
| 10/16/2025 03:30 PM UTC |
|
25-22 Arrowhead Drive Water Main Replacement OPWC #CM08AC
25-22 Arrowhead Drive Water Main Replacement
OPWC #CM08AC
The project consists of the replacement of the existing 6" and 8" cast iron water main with 8" and 12" C909 DR18 CL 150 PVC water main, bends and fittings; removal and replacement of pavement, curb and gutter, 8" and 12" valves, 3/4" tap for chlorination and testing, 41 water service branches, 8 fire hydrant assemblies, and storm sewer repairs. Note that project is not to begin until March 2, 2026.
State of Ohio Prevailing Wage Rates for Heavy Highway Construction apply.
Engineer's Estimate: $833,227
| 10/02/2025 03:30 PM UTC |
|
25-21 WTP Inline Process Monitoring Equipment Replacement
25-21 WTP Inline Process Monitoring Equipment Replacement
This project involves the replacement, installation and start-up of multiple inline process monitoring instruments, associated controllers, and supporting components. The selected vendor will be responsible for procurement, start-up and initial calibration, operator training, and warranty service support for all listed equipment.
The selected vendor will not be required to pay State of Ohio prevailing wage rates.
A pre-bid meeting is NOT scheduled. Site visits may be coordinated by contacting WTP Superintendent, Seth Epley at 937.498.8180 or sepley@SidneyOH.com prior to Friday, September 19, 2025 at 1:00 pm.
Estimate: $85,000
| 09/25/2025 05:00 PM UTC |
|
25-20 WWTP PLC Updates
25-20 WWTP PLC Updates
The project consists of updating two (2) PLCs. The first PLC is located in the Raw Pump Station, is an Allen Bradley SLC 504 with HMI. The second is an Allen Bradley SLC 500 and located in the Blower Building. The successful bidder will be responsible for purchasing two Allen-Bradley Compact Logix PLCs (or equal) that are compatible with the existing Compact Logix PLCs currently active at the Wastewater Treatment Plant (WWTP). The bidder will also be responsible for removing existing PLCs and installing the new PLCs in the existing control cabinets and transferring the existing ladder logic programming to the new units. This project also includes system startup, verification of all monitoring and control functions, and troubleshooting any programming issues to ensure proper operation of the WWTP Facility.
A pre-bid meeting is NOT scheduled. Site visits may be coordinated by contacting WWTP Superintendent, Barry Zerkle at 937.498.8721 or BZerkle@SidneyOH.com prior to 1:00 p.m. on Wednesday, August 27, 2025
The project will require the use of State of Ohio prevailing wage rates for Building Construction if the bid exceeds the threshold amount of $75,000.
Estimate of Probable Cost: $60,000
| 09/11/2025 03:30 PM UTC |
|
25-19 Aeration Basin Gates
25-19 Aeration Basin Gates
The project consists of installation of nine (9) gates on three (3) basins (3 gates/tank) including supplying anchors, grout, etc. The gates have been purchased by the City and are on-site for the installation. The basins will be completed individually to maintain plant operations.
A pre-bid meeting is NOT scheduled. Site visits may be coordinated by contacting WWTP Superintendent, Barry Zerkle at 937.498.8721 or BZerkle@SidneyOH.com prior to 1:00 p.m. on Friday, August 22, 2025
The project will require the use of State of Ohio prevailing wage rates for Building Construction if the bid exceeds the threshold amount of $75,000.
Estimate of Probable Cost: $62,000
| 08/28/2025 03:30 PM UTC |
|
25-12 SHE-Morrison Bridge Renovation
25-12
SHE-Morrison Bridge Renovation PID 117518
DBE GOAL 5%:
The project consists of renovating the Pratt truss and pin-connected bowstring bridge and relocating it from its current location to Sidney’s Tawawa Park.
Construction Estimate is $902.982.60
The project requires the payment of Federal Davis Bacon prevailing wage rates.
| 06/05/2025 03:30 PM UTC |
|
25-18 WWTP Raw Water Pump #5 Replacement
25-18 WWTP Raw Water Pump #5 Replacement
The project consists of the replacement of existing raw water pump #5 with a new water pump per specifications contained within the online Bidding Documents.
A pre-bid meeting is NOT scheduled. Site visits may be coordinated by contacting WWTP Superintendent, Barry Zerkle at 937.498.8721 or BZerkle@SidneyOH.com prior to 1:00 p.m. on Friday, May 16, 2025
The project requires the use of State of Ohio prevailing wage rates.
Estimate of Probable Cost: $72,000
| 05/22/2025 03:30 PM UTC |
|
25-17 Big Four Storm Outlet
25-17 Big Four Storm Outlet
The project consists of the replacement of 18” storm sewer on N. Main Avenue near the Big Four Bridge.
State of Ohio Prevailing Wage Rates apply.
Estimate: $42,400
| 05/15/2025 03:30 PM UTC |
|
25-11 Tilberry Run Drainage Ditch Improvements
25-11 Tilberry Run Drainage Ditch Improvements
The project consists of the regrading of ditch bank, the addition of gabion walls and erosion control measures.
State of Ohio Prevailing Wage Rates apply.
Estimate: $267,339
| 05/01/2025 06:30 PM UTC |
You have successfully created your Digital ID. It has been installed to your browser.
We recommend that you also download a backup of your Digital ID and save it securely to an external storage location, as this file must be installed again if you intend to use a different browser or computer for bidding, document signing, and solicitation management.
Learn more about managing your Digital ID.Click Install Backup ID to use your Digital ID in this location.
If you don't have a copy of your backup ID, but you have access to the computer and browser where it was first created, you can still create a backup ID to install to this location. For help, see how to back up your Digital ID.
If you don't have access to the original computer and browser, you can create a new Digital ID below.