35702700
City of Findlay Penrose Public Infrastructure Project
This public infrastructure project will include the new construction of 415 LF of 8-inch waterline, and 464 LF of sidewalk located within the Birchaven Complex as a part of the Blanchard Valley Health System.
Waterline Final Completion Date: August 31, 2020
Sidewalk Final Completion Date: December 31, 2021
Engineer’s Estimate: $86,295.00
| 07/16/2020 06:00 PM UTC |
32884500
City of Findlay HAN-CR236-0.00, PID100184
This project consist of widening out County Road 236 one lane to the east from Sandusky St. (SR568) to Tiffin Ave. (US224) as well as installing a multiuse path on the east side of the right of way. The widening of County Road 236 will reconfigure the roadway to a three lane road consisting of two drive lanes and a center turn lane. Along with the roadway widening a new 10 ft. wide multiuse path will be installed on the east side of the roadway from Sandusky St. to Tiffin Ave. New curb and gutter will be placed on this section of roadway, which will also include the relocation of existing storm structures. This project consist of, but not limited to; installing 2,450 SF of concrete sidewalk, 56,860 SF of asphalt multiuse path, 1208 CY of Asphalt Concrete Surface Course, 514 CY Asphalt Concrete Intermediate Course, aggregate base, new storm lines and structures, and grading and seeding.
The 2019 Ohio Department of Transportation (ODOT) Construction and Materials Specifications shall be followed. Required modifications to the ODOT specifications are noted herein. City of Findlay Specifications and Standard Drawings shall also be adhered to where applicable and are available at the City of Findlay Engineering Department, 318 Dorney Plaza, Findlay, OH 45840. Federal prevailing wages shall apply. The DBE goal for this project is 7%.
All Bidders shall submit a DBE Utilization Plan at the time of bid setting forth specific information demonstrating how the Bidder will achieve the DBE goal. By submitting a DBE Utilization Plan, the Bidder is affirming that they will be using the DBE firms identified in the Utilization Plan to meet the DBE contract goal. The DBE Utilization Plan shall be submitted online at:https://odot.formstack.com/forms/dbe_copy
Final Completion: on or before October 23, 2020
Engineering Estimate: $ 2,196,661.30
| 05/14/2020 06:00 PM UTC |
35293400
City of Findlay Airport Taxiway A (A4 to A6) Rehabilitation
Mill and overlay of Taxiway A from connector A4 through A^ at the Findlay Airport. There will be no geometry changes and the pavement markings will be updated to meet FAA Advisory Circular (AC) 150/5340-1M, Standards for Airport Markings, within the project limits.
Pre-Bid Meeting will be held on Wednesday, May 6, 2020 at 11:00 AM at the Findlay Airport Terminal Building located at 1615 Gary Street, Findlay, OH 45840. The meeting will be held outside.
There is a DBE Goal of 6% for the project
Engineer's Estimate (Base Bid)- $397,937.00
Completion Date: October 23, 2020
| 05/14/2020 06:00 PM UTC |
32876000
City of Findlay HAN-Lincoln & Blanchard Paths, PID104247
This project consist of a lane configuration of Blanchard Street between Sixth Street and Center Street to add dedicated bike lanes on the east and west side, reconstructed traffic signals at five signalized intersections, ADA compliant curb ramps, and resurfacing. In addition to the Blanchard Street lane configuration, a multi-use path will be constructed on the north side of Lincoln Street from Cory Street to Blanchard Street. The Lincoln Street portion of the project will also include upgrades to signalized pedestrian controls at 2 intersections and ADA compliant curb ramps. This project consist of, but not limited to, installing 30,000 SF of concrete sidewalk, 46,381 SY of pavement planning, 1933 CY of Asphalt Concrete Surface Course, 1200 LF of curb replacement aggregate base, new signs, upgrade 5 intersections, and grading and seeding.
The 2019 Ohio Department of Transportation (ODOT) Construction and Materials Specifications shall be followed. Required modifications to the ODOT specifications are noted herein. City of Findlay Specifications and Standard Drawings shall also be adhered to where applicable and are available at the City of Findlay Engineering Department, 318 Dorney Plaza, Findlay, OH 45840. Federal prevailing wages shall apply. The DBE goal for this project is 7%.
All Bidders shall submit a DBE Utilization Plan at the time of bid setting forth specific information demonstrating how the Bidder will achieve the DBE goal. By submitting a DBE Utilization Plan, the Bidder is affirming that they will be using the DBE firms identified in the Utilization Plan to meet the DBE contract goal. The DBE Utilization Plan shall be submitted online at:https://odot.formstack.com/forms/dbe_copy
Substantial Completion: on or before October 23, 2020
Final Completion: on or before August 13, 2021
Engineering Estimate: $ 2,170,854.00
| 05/13/2020 06:00 PM UTC |
35600100 - 2020 Annual Sewer Televising Program
City of Findlay 2020 Annual Sewer Televising Program-This program consists of performing closed circuit television inspection on various storm and sanitary sewers located within the City of Findlay. This program will assess the condition of the selected sewer lines, and present the information to the City of Findlay so that the information can be used to make decisions regarding rehabilitation and/ or replacement. The sewers will be rated by using a standardized field investigation approach to efficiently utilize time and resources when evaluating the selected sewers. This project shall consist of, but not limited to, sewer cleaning as necessary for proper sewer evaluating, CCTV recordings, evaluating and rating of recorded sewers, and electronic format submission of recorded/ evaluated sewers.
Completion Date: April 10, 2021
Engineering Estimate (Base Bid Only): $730,000
| 05/12/2020 06:00 PM UTC |
35691700
Madison Street and Monroe Avenue Sanitary Sewer Replacement
This project consists of replacing an existing 8-inch Vitrified Clay Pipe with new 8-inch SDR35 pipe on the South side of both Madison Street and Monroe Avenue between North Main Street and Morey Avenue. There are 89 existing laterals that will need to be tied into the new Sanitary Sewer. The existing 8-inch sewer will need to remain operational until all the existing lateral are tied into the new sewer. Upon completion, the existing 8” sanitary sewer will be abandoned by grouting.
Final Completion Date: August 14, 2020
Engineer’s Estimate: $426,500
| 04/14/2020 06:00 PM UTC |
35795300
City of Findlay Sixth Street Waterline Replacement.
This project consists of replacing a 10-inch waterline on Sixth Street from Main Street to Eagle Creek. The project consist of two sections of 10-inch waterline and one section of 16-inch waterline. The 10-inch sections will run from Main Street to Park Street (waterline will be ran on the north side in the grass) and from Blanchard Street to Eagle Creek (waterline will be ran in the westbound lane). The section from Park Street to Blanchard Street will consist of a 16-inch waterline install that will be ran in the westbound lane of Sixth Street. The 16-inch waterline will be tied onto an existing 16-inch stub at Blanchard Street and will be jack and bored under the CSX railroad tracks to Park Street.
This project shall consist of, but not limited to, 695 LF of 16-inch C900 waterline, 60 LF of 22-inch casing jack and bore, 1680 LF of 10-inch Type B C909 waterline, 1350 LF of 10-inch Type C C909 waterline, 200 LF of 6-inch C909 waterline, full depth pavement repair, waterline tie-ins, waterline abandonments, fire hydrant removal, hydrant replacement, misc. fittings, seeding and mulching.
Substantial Completion Date: August 7, 2020
Final Completion Date: August 21, 2020
Engineer’s Estimate: $550,000.00
| 03/11/2020 06:00 PM UTC |
35793300
City of Findlay Olive Street 16-inch Waterline Extension.
This project consists of installing a new 16-inch C905 waterline on Olive Street, running in the eastbound lane of Olive Street. The waterline will start from a 16-inch stub on Park Street and will extend to an existing 16-inch stub at Brookside Drive. The new waterline will need to be jack and bored under the CSX Railroad and Horizontal Directional Drill under Eagle Creek. This project shall consist of, but not limited to, 1760 LF of 16-inch C905 waterline, jack and bore 60 LF of 22-inch casing pipe, 225 LF of 16-inch directional drill, 60 LF of 8-inch waterline, full depth pavement repair, waterline tie-ins, waterline abandonments, fire hydrant removal, hydrant replacement, misc. fittings, seeding and mulching.
Final Completion Date: August 21, 2020
Engineer’s Estimate: $525,000.00
| 03/04/2020 07:00 PM UTC |
32593900
City of Findlay Country Club Drive Landslide Repair
This project will consist of repairing the existing landslide along Country Club Drive and adjacent to the Blanchard River. This project will also consist of modifications to the existing storm sewer that outlets to the Blanchard River. Within the project area there are overhead power lines, which will effect some of the work.
The project will be awarded to the lowest and most responsive bidder based on the Grand Total Price of the Base Bid and any accepted Alternates as selected by the City of Findlay.
Substantial Completion: March 30, 2020
Final Completion: August 18, 2020
Engineering Estimate: $ 230,000 (Base Bid)
| 02/26/2020 07:00 PM UTC |
35795200
City of Findlay Rutherford Avenue 6-inch Waterline Replacement.
This project consists of installing a new 6-inch C909 waterline on Rutherford Avenue, running along the north side of the roadway, from Main Street to Terrace Lane. From the existing 6-inch waterline located on Main Street the proposed waterline will extend east toward Terrace Lane. This project shall consist of, but not limited to, 1200 LF of 6-inch C909 waterline, full depth pavement repair, waterline tie-ins, waterline abandonments, fire hydrant removal, hydrant replacement, misc. fittings, seeding and mulching.
Substantial Completion Date: May 22, 2020
Final Completion Date: May 29, 2020
Engineer’s Estimate: $132,000.00
| 02/19/2020 07:00 PM UTC |
You have successfully created your Digital ID. It has been installed to your browser.
We recommend that you also download a backup of your Digital ID and save it securely to an external storage location, as this file must be installed again if you intend to use a different browser or computer for bidding, document signing, and solicitation management.
Learn more about managing your Digital ID.Click Install Backup ID to use your Digital ID in this location.
If you don't have a copy of your backup ID, but you have access to the computer and browser where it was first created, you can still create a backup ID to install to this location. For help, see how to back up your Digital ID.
If you don't have access to the original computer and browser, you can create a new Digital ID below.