City of Findlay
318 Dorney Plaza Rm 304, Findlay, OH 45840
(419) 424-7121
318 Dorney Plaza Rm 304, Findlay, OH 45840
(419) 424-7121
Name * | Description | |
---|---|---|
Number | Deadline |
---|---|
6
Item #6 - Ferrous Chloride- The City of Findlay is accepting proposals for Fluorosilicic Acid for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 AM UTC |
68
Item #68 - Copper Sulfate Pentahydrate Liquid - The City of Findlay is accepting proposals for Copper Sulfate Pentahydrate Liquid for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 AM UTC |
33
Item #33 - Airport Fuel- The City of Findlay is accepting proposals for Airport Fuel for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 AM UTC |
17
Item #17-Crushed Stone - The City of Findlay is accepting proposals for Crushed Stone for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
1601
Item #1601-Ready Mix Concrete - The City of Findlay is accepting proposals for Ready Mix Concrete for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
64
Item #64 - Municipal Building Cleaning - The City of Findlay is accepting proposals for Municipal Building Cleaning for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
66
Item #66 -Copper Sulfate Pentahydrate Crystals - The City of Findlay is accepting proposals for Copper Sulfate Pentahydrate Crystals for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
2801
Item #2801 - Waterline Tapping Gates - The City of Findlay is accepting proposals for Waterline Tapping Gates for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
27
Item #27 - Waterline Gate Valves - The City of Findlay is accepting proposals for various sizes and quantities of waterline gate valves to be supplied and delivered for the period of January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
13
Item #13 - Asphalt Concrete - The City of Findlay is accepting proposals for Asphalt Concrete for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
7
Item #7-Liquid Carbon Dioxide (BULK) - The City of Findlay is accepting proposals for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
2802
Item #2802 - Waterline Tapping Sleeves - The City of Findlay is accepting proposals for Waterline Tapping Sleeves for the period January 1, 2026, to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
26
Item #26 -Fire Hydrants- The City of Findlay is accepting proposals for Fire Hydrants for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
1
Item #1-Pebble Lime Bulk - The City of Findlay is accepting proposals for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
2401
Item #2401-Water Meter Lids - The City of Findlay is accepting proposals for Water Meter Lids for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
1603
Item #1603-Class C Concrete - The City of Findlay is accepting proposals for Class C Concrete for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
69
Item #69 -Large Diameter and Gate Valve
The City of Findlay is accepting proposals for
Large Diameter and Gate Valves with electric actuators, for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
63
Item #63 - C909 Plastic Pipe - The City of Findlay is accepting proposals for furnishing and delivery of C909 plastic pipe for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
34
Item #34 - Jet-A Turbine Aviation Fuel - The City of Findlay is accepting proposals for supply and delivery of an estimated 200,000 gallons of Jet-A Turbine Aviation Fuel, meeting latest ASTM D-1655 specifications, to the Findlay Airport at 1615 Gray Street, during the period of January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
32
Item #32 - Vehicle & Equipment Fuel (Gasoline & Diesel)- The City of Findlay is accepting proposals for Vehicle & Equipment Fuel (Gasoline & Diesel) for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
1602
Item #1602-CDF - The City of Findlay is accepting proposals for CDF for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
14
Item #14- Liquid Asphalt- The City of Findlay is accepting proposals Liquid Asphalt for the period of January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
402
Item #402 - Sodium Hypochlorite (WTP) - The City of Findlay is accepting proposals for Sodium Hypochlorite (WTP) for the period January 1, 2026 to December 31, 2026.
| 10/16/2025 06:00 PM UTC |
Number | Deadline |
---|---|
32810900-B
City of Findlay 2021 Annual Resurfacing Program-Contract B (Asphalt)
This contract is for asphalt work only, consisting of pavement planning (approximately 43,510 SY) and asphalt resurfacing (approximately 2,490 CY) on various streets within the City of Findlay or Hancock County. Incidental items include, but not limited to, are adjustment of manholes, and joint sealing. Other minor work is described in the details for each segment of pavement. The project will be split up into two different groups to ensure some of the larger sections of road are completed before school is in session.
The project will be awarded to the lowest and most responsive bidder based on the Grand Total Price of the Base Bid and any accepted Alternates as selected by the City of Findlay.
Projected Start Date for Each Group:
Group One: On or Before June 21, 2021
Group Two: On or Before August 9, 2021
Final Completion for Each Group:
Group One: On or Before August 6, 2021
Group Two: On or Before October 15, 2021
Engineering Estimate: $ 554,000 (Base Bid)
| 03/10/2021 07:00 PM UTC |
32810900-A
City of Findlay 2021 Annual Resurfacing Program-Contract A (Concrete)
This project consists of nearly 20,430 (LF) of curb removal and replacement on various streets within the City of Findlay in Hancock County. Incidental items include necessary sidewalk or curb ramp replacement (approximately 12,740 SF), concrete drive replacement (approximately 1165 SY), asphalt drive replacement (approximately 430 SY), adjustment of manholes and catch basins, grading and seeding. Other minor work is described in the details for each segment of roadway. The project will be split up into two different groups to ensure some of the larger sections of road are completed before school is in session.
The project will be awarded to the lowest and most responsive bidder based on the Grand Total Price of the Base Bid and any accepted Alternates as selected by the City of Findlay.
Final Completion for Each Group:
Group One: On or Before July 2, 2021
Group Two: On or Before August 6, 2021
Engineering Estimate: $ 656,000 (Base Bid)
| 03/09/2021 07:00 PM UTC |
35601200
City of Findlay Bittersweet Dr. and Bluebonnet Dr. Sanitary Sewer
This project on Bittersweet Drive and Bluebonnet Drive consist of installing a new 8-inch sanitary sewer from Lilac Lane to Western Avenue on each of the respective streets. The area is currently not served by any sanitary sewer and the new sanitary will be installed to allow homeowners to tap into the new public line. On each of the streets the sanitary will be placed in the grass area about 9-10 Ft. off the edge of roadway. Due to the location and the depth of the sanitary sewer, the sewer is expected to be placed in bedrock at times. The new sanitary sewers will tie into an existing sanitary sewer manhole with an outside drop and will extend to the west towards Western Avenue. The sanitary sewers range in depth from 10 Ft to 5 FT, with laterals being installed at each property.
This project shall consist of, but not limited to, 3670 LF of 8-inch sanitary sewer, 44 sewer service laterals, full depth trench repair (4-inch thickness), 2 sanitary tie ins with outside drops, 14 sanitary manhole structures, 1170 CY of rock excavation, driveway replacement, seeding and mulching.
This project is funded by City of Findlay Sewer Funds. Bidders shall be aware of the required Equal Employment Opportunity Requirements as well as the State Prevailing Wages that apply to this project. Domestic steel use requirements also apply to this project as specified in Section 153.011 of the Ohio Revised Code. A copy of Section 153.011 can be obtained from any office of the Ohio Department of Administrative Services.
Final Completion Date: September 3, 2021
Engineer’s Estimate: $640,550.00
| 03/03/2021 07:00 PM UTC |
35603400
Northside Sewer Televising - This project consists of performing closed circuit television inspection on various sanitary sewers located within the City of Findlay. This program will assess the condition of the selected sewer lines, and present the information to the City of Findlay so that the information can be used to make decisions regarding rehabilitation and/ or replacement. The sewers will be rated by using a standardized field investigation approach to efficiently utilize time and resources when evaluating the selected sewers. This project shall consist of, but not limited to, sewer cleaning as necessary for proper sewer evaluating, CCTV recordings, evaluating and rating of recorded sewers, and electronic format submission of recorded/ evaluated sewers.
Completion Date: August 6th, 2021
Engineering Estimate (Base Bid Only): $38,480.75
| 03/03/2021 07:00 PM UTC |
35500500
City of Findlay Chapel Drive Storm Sewer
This storm sewer project on Chapel Drive consists of installing a new 12-inch storm sewer on the west side of the roadway to help alleviate storm water runoff. The storm sewer will start at an existing storm manhole at West Hobart Avenue and will stretch to the south towards West Edgar Avenue. At W. Edgar Avenue two catch basins will be placed on the east side of the intersection to collect roadway runoff.
This project shall consist of, but not limited to, 473 LF of 12-inch storm sewer, 87 LF of 8-inch storm sewer, full depth trench repair (4-inch thickness), storm line tie-ins, 4 storm structures, 300 SF of sidewalk replacement, seeding and mulching.
This project is funded by City of Findlay Storm Sewer Funds. Bidders shall be aware of the required Equal Employment Opportunity Requirements as well as the State Prevailing Wages that apply to this project. Domestic steel use requirements also apply to this project as specified in Section 153.011 of the Ohio Revised Code. A copy of Section 153.011 can be obtained from any office of the Ohio Department of Administrative Services.
Final Completion Date: June 24, 2021
Engineer’s Estimate: $93,000.00
| 02/26/2021 07:00 PM UTC |
32894300
City of Findlay, Logan Avenue Reconstruction Phase III, OPWC FY20
This reconstruction project on Logan Avenue will be an extension to the previous two projects that were performed east of the proposed work site. Logan Avenue will be reconstructed from Tappan Avenue to Harrison Street. The existing roadway will be lowered by 6-10 inches to allow proper grading for a newly built roadway with straight curb extended to the west. A new 4 ft. wide concrete sidewalk will be installed on both sides of the roadway, and the grass area between the new sidewalk and curb will be regraded to properly drain. Along with the reconstruction of the roadway a new 8-inch waterline will be installed on the north side of Logan Avenue and the existing storm sewer on the south side of Logan Avenue will be extended to Harrison Street.
This project shall consist of, but not limited to, 1230 LF of 8-inch C909 waterline, 125 LF of 12-inch waterline, waterline tie-ins, waterline abandonments, fire hydrant installation, misc. fittings, seeding and mulching, 185 LF of 30-inch storm sewer, 380 LF of 24-inch storm sewer, 335 LF of 15-inch storm sewer, 250 LF of 12-inch storm sewer, 18 storm structures, 2600 LF of straight curb, 6,940 SF of sidewalk, drive approach replacement, roadway excavation, embankment, and 375 CY of asphalt.
This project is funded by City of Findlay Water, Sewer, and Capitol Funds as well as Ohio Public Works Commission (OPWC). Bidders shall be aware of the required Equal Employment Opportunity Requirements as well as the State Prevailing Wages that apply to this project. Domestic steel use requirements also apply to this project as specified in Section 153.011 of the Ohio Revised Code. A copy of Section 153.011 can be obtained from any office of the Ohio Department of Administrative Services.
Final Completion Date: October 1, 2021
Engineer’s Estimate: $726,700
| 02/12/2021 07:00 PM UTC |
32801400
City of Findlay HAN-Findlay Bright Road Phase I, PID108768
This project consists of nearly 2,513 linear feet of curb removal and replacement and/or pavement planning (approximately 42,187 SY) and resurfacing (approximately 2,347 CY) on Bright Road within the City of Findlay and Hancock County. Incidental items include necessary sidewalk or curb ramp replacement (approximately 3,480 SF), treatment of shoulders, adjustment of manholes and catch basins, and grading and seeding. Other minor work is described in the details for each segment of pavement.
The 2019 Ohio Department of Transportation (ODOT) Construction and Materials Specifications shall be followed. Required modifications to the ODOT specifications are noted herein. City of Findlay Specifications and Standard Drawings shall also be adhered to where applicable and are available at the City of Findlay Engineering Department, 318 Dorney Plaza, Findlay, OH 45840. Federal prevailing wages shall apply. The DBE goal for this project is 7%.
All Bidders shall submit a DBE Utilization Plan at the time of bid setting forth specific information demonstrating how the Bidder will achieve the DBE goal. By submitting a DBE Utilization Plan, the Bidder is affirming that they will be using the DBE firms identified in the Utilization Plan to meet the DBE contract goal. The DBE Utilization Plan shall be submitted online at:https://odot.formstack.com/forms/dbe_copy
Final Completion: on or before August 6, 2021
Engineering Estimate: $ 633,894.25
| 01/26/2021 07:00 PM UTC |
32803100 - Dr. Martin Luther Kind Jr. Parkway
Dr. Martin Luther King Jr. Parkway
***Pre-bid Meeting will be December 8, 2020 at 2:00pm in the City of Findlay Municipal Building.
Project Description:
Improvement of two intersections along Martin Luther King Jr. Parkway to raise the roadway profile. Perform necessary related work including drainage, retaining walls, drives, walk and signal improvements.
Final Completion: July 30, 2021
Engineering Estimate: $1,667,577.54
| 12/18/2020 07:00 PM UTC |
65
Item #65 - Motor and Pump Repair/Rebuilding - The City of Findlay is accepting proposals for Motor and Pump Repair/Rebuilding for the period January 1, 2021 to December 31, 2021.
| 12/16/2020 07:00 PM UTC |
1
Item #1 - Pebble Lime (BULK) - The City of Findlay is accepting proposals for Pebble Lime (BULK) for the period January 1, 2021 to December 31, 2021.
| 12/16/2020 07:00 PM UTC |
You have successfully created your Digital ID. It has been installed to your browser.
We recommend that you also download a backup of your Digital ID and save it securely to an external storage location, as this file must be installed again if you intend to use a different browser or computer for bidding, document signing, and solicitation management.
Learn more about managing your Digital ID.Click Install Backup ID to use your Digital ID in this location.
If you don't have a copy of your backup ID, but you have access to the computer and browser where it was first created, you can still create a backup ID to install to this location. For help, see how to back up your Digital ID.
If you don't have access to the original computer and browser, you can create a new Digital ID below.