Capital Project Number CP3414
CITY OF LAKE CHARLES, LOUISIANA
SOUTHWEST WATER TREATMENT PLANT
BACK-UP POWER IMPROVEMENTS
CAPITAL PROJECT NUMBER CP3414
HMGP GRANT NO. DR-4559-43
I. Scope of Services:
Contractor shall complete all Work as specified or indicated in the Contract Documents for the Southwest Water Treatment Plant – Back-Up Power Improvements project. The Work includes, but is not limited to, the following:
• Removal and Replacement of the Existing Stand-By Generator with Two (2) Parallel 600kW Stand-By Diesel Generators complete with 2,500A, 480VAC, 3PH Paralleling Switchgear.
• Removal and Disposal of the Existing Manual Transfer Switch and Replacement with 2,500A, 480VAC Delayed Transition Automatic Transfer Switch.
• Installation of Low Voltage Panelboard for Supply to Generator Appurtenances.
• Interconnections to Owner’s SCADA for Generator Monitoring.
• Miscellaneous Civil and Electrical Work as Required to Complete the Work.
| 11/18/2025 08:45 PM UTC |
| Number | Deadline |
|---|---|
|
RFP #2025-06 File ID #334-24
Project Management and Administrative Services for the FEMA Disaster Recovery Programs and Other Federally or State Funded Initiatives
| 11/05/2024 08:45 PM UTC |
|
Capital Project No. 3404
City of Lake Charles, Louisiana
Wastewater Treatment Plant D Disinfection Facility Improvements
Capital Project No. 3404
Scope of Services:
The City of Lake Charles owns and operates the Wastewater Treatment Plant D, located at 3820 Tank Farm Rd. In the draft permit renewals for each facility, the Department of Environmental Quality (DEQ) introduced a new effluent discharge limitation for Enterococci bacteria. Manchac has consulted with the existing disinfection equipment manufacturer and determined that the equipment will not meet the new Enterococci limits as mandated by DEQ.
This project will include the removal and replacement of the existing disinfection treatment equipment with a new Sodium Hypochlorite and Sodium Bisulfite disinfection basin. Work includes the construction of a new contact basin, new sodium hypochlorite storage building, renovations to an existing sodium bisulfite building, installation of new gravity sewer, and misc. piping.
| 11/05/2024 08:45 PM UTC |
|
DR002
City of Lake Charles, Louisiana
Lake Charles Public Works New Facility Phase 1
DR002
Scope of Project
Build a new 15,000 SF office building on an existing undeveloped site. Project to include parking, generator, underground drainage, drainage swales and detention areas, a new lift station and other work as noted in plans and specifications.
| 11/05/2024 08:45 PM UTC |
|
Project No. 2024-739 DR010
City of Lake Charles, Louisiana
Project No. 2024-739
DR010
LCFD Fire Training Facility Demo & Earthwork
PROJECT SUMMARY: The general scope of work for this project consists of demolition and removal of the former school building and improvements as shown on the plans. Once the building demolition has occurred, the removal and disposal of the of the top 2 feet of existing soil within the limits shown on the plans, followed by the furnishing and installation of lime conditioned select fill to the proposed elevation identified. The select fill will be installed in multiple lifts and compacted to the required density as monitored by engineer and testing laboratory.
| 10/15/2024 07:45 PM UTC |
|
CP 3492
City of Lake Charles, Louisiana
Mallard Golf Club
Driving Range Lighting
CP 3492
SCOPE OF WORK
A. Driving Range Lighting
1) Installation of light poles, conduit, and all associated electrical.
B. Site Access
1) Stabilization and protection of site access drive for material and light pole delivery.
2) Repair of concrete paving damaged by site access
3) Repair of landscaping and regrading of site to return to its preconstruction state.
PRODUCTS, WORKS AND SERVICES PROVIDED BY THE OWNER
A. Testing lab services.
INSTALLATION OF OWNER PROVIDED AND ALLOWABLE PRODUCTS
A. The contractor shall provide accessories and installation of such products, unless specified otherwise.
| 10/15/2024 07:45 PM UTC |
|
2024-26
Request for Qualifications for Consultant Services in Response to SAFE STREETS AND ROADS FOR ALL (SS4A) – SAFETY ACTION PLAN
| 09/03/2024 07:45 PM UTC |
|
CP 3274
City of Lake Charles, Louisiana
Gauthier Rd Waterline Extension CP 3274
I. Scope of Services:
Contractor shall complete all Work as specified or indicated in the Contract Documents for Gauthier Road Waterline Extension project. The Work includes, but is not limited to, the following:
o Furnishing and installing of approximately 1300 linear feet of 18-inch PVC and 900 linear feet of 20-inch HDPE water main from Nelson Road to Southpark Drive.
| 07/16/2024 07:45 PM UTC |
|
Capital Project Number CP3070
CITY OF LAKE CHARLES, LOUISIANA
WWTP B/C OXIDATION DITCH REPAIRS & IMPROVEMENTS
CAPITAL PROJECT NUMBER CP3070
Scope of Services:
Contractor shall complete all Work as specified or indicated in the Contract Documents for the WWTP B/C Oxidation Ditch Repairs and Improvements Project. The Work includes, but is not limited to, the following:
• Remove and replace all bearings and couplings in Oxidation Ditch No. 1.
• Remove 60 HP direct coupled motors/gearboxes (6 EA) from Oxidation Ditch No. 1 and replace with 60 HP belt driven motors/gearboxes (6 EA).
• Furnish and install 100A NEMA 4XSS disconnect switch near each motor at Oxidation Ditch No.’s 1 and 2 (12 EA).
• Furnish and install CAT6 ethernet cable in existing 1” conduit (2 EA) for wireless gateway monitoring system.
| 07/02/2024 07:45 PM UTC |
|
Project No. 2024-738 Capital Project No. 3493
Project No. 2024-738
Capital Project No. 3493
Ryan Street Drainage Improvements –
Clarence to Kirby St
City of Lake Charles, Louisiana
PROJECT SUMMARY: The general scope of work for this project includes the rehabilitation and reconstruction of existing drainage infrastructure on Ryan Street from Clarence Street to Kirby Street. This work includes the installation of new drainage pipe and boxes, rehab of existing drainage where possible, and the associated roadway pavement repairs to facilitate the drainage improvements.
| 07/02/2024 07:45 PM UTC |
|
2024-24
Transit Advertising Program for Lake Charles Transit
| 06/04/2024 07:45 PM UTC |
You have successfully created your Digital ID. It has been installed to your browser.
We recommend that you also download a backup of your Digital ID and save it securely to an external storage location, as this file must be installed again if you intend to use a different browser or computer for bidding, document signing, and solicitation management.
Learn more about managing your Digital ID.Click Install Backup ID to use your Digital ID in this location.
If you don't have a copy of your backup ID, but you have access to the computer and browser where it was first created, you can still create a backup ID to install to this location. For help, see how to back up your Digital ID.
If you don't have access to the original computer and browser, you can create a new Digital ID below.