General Info

Business Logo

City of Lake Charles

326 Pujo Street, Lake Charles, LA 70601
(337) 491-1263


Standard Documents

Name * Description
0 Documents

Upcoming Solicitations

Number Deadline
0 Solicitations

Closed Solicitations

Number Deadline
CP3406
City of Lake Charles, Louisiana Corbina Road Water Main Extension – James Court to W. Prien Lake Road CP3406 SCOPE OF WORK: Project scope consists of the installation of a proposed watermain along Corbina Road in Lake Charles, LA. The project scope shall include, but it not limited to, the installation of a 16” diameter watermain, gate valves, fire hydrants, ductile iron fittings, material, equipment and labor. The installation of the proposed watermain by horizontal and directional drilling will be required for approximately 1,100 linear feet. PROJECT LIMITS: The project limits are along the eastern side of Corbina Road extending from James Court to E. Prien Lake Road.
04/04/2023 07:45 PM UTC
Capital Project Number CP3251
City of Lake Charles University Area Blue Sub-Basin Sewer Rehabilitation Capital Project Number CP3251 I. Background: The University area is one of the oldest areas in the City of Lake Charles. Wastewater flow studies have indicated excessive inflow and infiltration during rain events, causing peak flows up to 14 times the average daily wastewater rate. II. Scope of Services: Based on review of the CCTV data of the sewer line cleaning and CCTV project within the University area, the assessed pipelines have been designated as critically deficient and priority one deficient. Following review of the assessment the following scope of work has been developed. A. There is approximately 3,215 LF of 8” sewer pipe that has been identified as critical deficiencies and an additional 7,948 LF of 8” sewer pipe that has been identified as priority one deficiencies that will be rehabilitated as part of the base bid of this project. B. Manchac Consulting Group, Inc. will analyze the CCTV data provided, and rehabilitation methods will be refined upon review of the CCTV data during final design. Rehabilitation methods include pipe bursting, point repairs, cured-in-place lining, and manhole lining.
04/04/2023 07:45 PM UTC
Project No. 2022-720 Capital Project No. PR0002
Project No. 2022-720 Capital Project No. PR0002 North Beach Improvements City of Lake Charles, LA This project provides for an improved parking area along the South l-10 service road that will serve a proposed future commercial development. This development is located west of the existing Wildlife and Fisheries building and East of the current sand beach. Additional items anticipated with this project include the following: • Re-configure the existing north beach parking lot exit. This exit will be shifted westerly to comply with LA DOTD separation requirements. • Provide sewer and water service taps for future commercial development prior to hard surfacing the parking area.
03/14/2023 07:45 PM UTC
HL-14
City of Lake Charles, Louisiana Lake Charles Civic Center Hurricane Laura Restoration – Exterior Repairs HL-14 1. Replace damaged and missing stucco wall panel system on South Wall. Restore to pre- disaster conditions. Color of finish on wall panels shall be selected by Owner. All existing similar panels on South wall will be patched and recoated with similar finish. Seal all joints. Approx 1300 SF 2. Replace existing temporary stud wall in area of missing wall panels at upper south wall and replace with new structural steel studs, insulation, and fireproofing. 3. Repair and replace 2’-3’ tall aggregate panel where missing at top of South Wall. Match existing if possible. Seal and paint to match existing aggregate fascia panel, approx. 100 LF. Provide structural steel stud framing. Seal all joints. 4. Repair damaged balcony walkway and railing at South elevation. Install new structural steel connection to support existing beams. (2 connectors) 5. Replace plaster soffit where removed at third level on the East side and where damaged under upper-level canopy at North wall. Replace plaster soffits at south end under failed walkway canopy where removed to repair structure. 6. Repair any damaged aggregate wall panels where holes occur. Approx. includes 6 locations 7. Miscellaneous repairs to aluminum storefront entrances. 8. Clean all surfaces and waterproof all exterior surfaces.
03/14/2023 07:45 PM UTC
Capital Project Number CP3246
City of Lake Charles Wastewater System Improvements Salene Road, Lawrence Lane, and A. Miller Road Capital Project Number CP3246 I. Scope of Services: A. There are currently no City wastewater services available on Salene Road, Lawrence Lane, and A. Miller Road. It is the City’s desire to provide sewer service for the residents on these streets. Due to the higher capital costs associated with conventional gravity collection systems, it is the intent of the City to provide a low pressure sewer collection system for this area. B. Three forcemains will be designed as part of this project to allow for each home to connect to one of the forcemains via low pressure wastewater pump. One forcemain will be located on each street and will discharge into the existing manholes located at the end of each street near Big Lake Road. The wastewater pump located at each home and a small diameter forcemain from each home that would connect to the City’s new forcemains will not be designed as part of this project. C. The Work includes, but is not necessarily limited to, the following: • Directional drill of 2,264 linear feet of 2” HDPE and 766 linear feet of 3” HDPE sewer forcemain. • Directional drill 800 linear feet of 1.25” HDPE and open cut 140 LF of 1.25” HDPE lateral pipe. • Install 50 lateral kits and service connections to new sewer forcemain. • Coating approximately 27 vertical feet of existing manholes. • Procurement and Furnishing of 15 E-One Grinder Stations to COLC Wastewater Department
02/28/2023 08:45 PM UTC
Capital Project Number CP3262
CITY OF LAKE CHARLES, LOUISIANA SOUTHEAST WATER TREATMENT PLANT NEW WATER TREATMENT FACILITY CAPITAL PROJECT NUMBER CP3262 I. Scope of Services: Contractor shall complete all Work as specified or indicated in the Contract Documents for Southeast Water Treatment Plant – New Water Treatment Facility project. The Work includes, but is not limited to, the following: • Construction of a new groundwater treatment facility predicated on the removal of iron and manganese which includes the following major components to facilitate the production, treatment, and distribution of potable water: o Four (4) water production wells. o Four (4) horizontal pressure filters. o Two (2) concrete, ground storage tanks. o Four (4) high service pumps. o Two (2) backwash pumps. o One (1) backwash recovery clarifier. o One (1) backwash recovery pump station. o One (1) sludge detention lagoon. o Chemical feed systems (chlorine, pot perm, fluoride, phosphate, and caustic). o Onsite backup generator with automatic transfer switch. o Buildings (Chemical Feed, Chlorine, and Filter Buildings). o Miscellaneous civil, mechanical, electrical, and SCADA components.
02/14/2023 08:45 PM UTC
Project No. 2022-722 Capital Project No. 3428
Project No. 2022-722 Capital Project No. 3428 Various Citywide Drainage & Ancillary Infrastructure Improvements Phase 2 City of Lake Charles, LA The general scope of work for this project is demolition of site paving/foundations and utilities and reconstruction of various pavements, including drainage, sewer, water, and electrical improvements adjacent to the existing parking garage on North Beach.
02/14/2023 08:45 PM UTC
Project No. 2019-693 Capital Project No. 3308
Project No. 2019-693 Capital Project No. 3308 Downtown Streetscape Phase II Bilbo St. between Division St. & Mill St. City of Lake Charles, LA The general scope of work for this project consists of reconstructing sidewalks at the intersections of Bilbo Street and Division Street and Bilbo Street & Mill Street in preparation of the new Woodring Apartment development in the 600 block of Bilbo Street. This will be accomplished by: • Reconstructing the sidewalks at the intersections to provide ADA compliant handicap sidewalk ramps • Removing the traffic signals at these intersections and converting them to 4-way stops • Constructing “bulb-outs” to further define existing streetside parking • Increasing the pavement width on the East side of Bilbo Street from Division Street to Mill Street to provide for additional parallel, streetside parking • Salvaging the existing bus-stop assembly and constructing a new bus-stop site on Mill Street This work will also require installation of new drainage features as well as the associated pavement work.
01/31/2023 08:45 PM UTC
Project #CP3335
City of Lake Charles, Louisiana Nellie Lutcher Memorial Pocket Park City of Lake Charles Project #CP3335 The project scope consists of the new construction of a pocket park. Work scope includes earthwork, paving, fencing, landscaping, and limited electrical items.
12/20/2022 08:45 PM UTC
CAPITAL PROJECT NO. HL-24, 25A, 29E, 29G, 29H, 32, 33, 81A, 81.D.1, 81M, 126E, 126C, 126D, 126J, 126K, 126F
CITY OF LAKE CHARLES, LOUISIANA WASTEWATER TREATMENT PLANTS MISCELLANEOUS BUILDING REPAIRS CAPITAL PROJECT NO. HL-24, 25A, 29E, 29G, 29H, 32, 33, 81A, 81.D.1, 81M, 126E, 126C, 126D, 126J, 126K, 126F I. Background: Gusting winds, debris impacts, and heavy rain, associated with Hurricane Laura, incurred minimal to severe damages to multiple buildings located at Wastewater Treatment Plants A, B/C, and D. This project will serve to provide necessary repairs to reinstate building functionality to pre-storm conditions. Scope items have also been identified that would serve to upgrade these antiquated systems to the latest codes and standards. II. Scope of Services: Design and implementation of building repairs, in response to damages incurred as a result of Hurricane Laura (DR-4559-LA), to pre-storm conditions and regulations as imposed by governmental bodies with the appropriate jurisdictional authority. This Work shall include the following: Wastewater Treatment Plant A (128 W. Railroad Ave., Lake Charles, LA 70601) • Office/Administration/Blower Pump Room Building (Insurance SOV No. 081A) • Storage Building No.1 (Insurance SOV NO. 081.D.1) • Sludge Processing Building (Insurance SOV No. 081M) Wastewater Treatment Plant B/C (1132 W. 18th St., Lake Charles, LA 70601) • Equipment Building (Insurance SOV No. 024) • Portable Building (Insurance SOV NO. 25A) • RAS/WAS Pump Station (Insurance SOV No. 029E) • Motor Control Center No. 1 Building (Insurance SOV No. 029G) • Motor Control Center No. 2 Building (Insurance SOV No. 029H) • Electrical Storage Building (Insurance SOV No. 32) • Portable Building (Insurance SOV No. 33) Wastewater Treatment Plant D (3820 Tank Farm Rd., Lake Charles, LA 70601) • Press Building (Insurance SOV No. 126C) • Tertiary Filter Building (Insurance SOV No. 126D) • Maintenance Building (Insurance SOV No. 126E) • Control Room Building (Insurance SOV No. 126F) • MCC Building (Insurance SOV No. 126J) • MCC Building (Insurance SOV No. 126K) • Oxidation Ditch No. 1 (Insurance SOV No. 126.A.1) Design services shall be as per the City of Lake Charles A&E Manual.
12/20/2022 08:45 PM UTC
71 - 80 of 380 Solicitations
1 2 3 4 5 6 8 10 11 12 37 38