Name * Description
How to find bid results.pdf (78.7 KB)
How To Find Bid Results
8829PlanHolders05222026.pdf (84 KB)
Contract 8829 - Sidewalk Curb & Gutter 2026
8830PlanHolders05222026.pdf (88.2 KB)
Contract 8830 - Bridge Repairs - 2026
9787PlanHolders05222026.pdf (85.9 KB)
Contract 9787 - Newville Park Redevelopment
4 Documents

Upcoming Solicitations

Number Deadline
8830 - Bridge Repairs - 2026
The work under this contract shall include, but is not limited to concrete deck repairs, expansion joint replacement, expansion plate replacement, polymer overlay, guardrail installation, storm sewer pipe and structure installation, excavation, gravel base course, asphalt pavement, concrete curb & gutter, concrete sidewalk, shared-use path installation, soil restoration, and pavement markings.
06/04/2026 07:00 PM UTC
8829 - Sidewalk, Curb & Gutter, and Concrete Pavement Patches, Citywide Installation and Repair - 2026
The Contractor shall perform work at various locations throughout the City, as ordered by the Common Council, or as directed by the Engineer. This work includes replacing defective sidewalk and curb and gutter, concrete pavement repairs, sidewalk ramps including detectable warning fields (supplied by the Contractor), Metro Transit bus pads, and other associated work. A list of approved locations and detail drawings are included with these Special Provisions. The list, however, is not a final list. Additional locations may be added.
06/04/2026 07:00 PM UTC
9787 - Newville (Kenneth) Park Redevelopment
This project consists of installation of new game equipment, benches, concrete paths, grading and preparation of landscape beds at Newville (Kenneth) Park.
06/11/2026 07:00 PM UTC
3 Solicitations

Closed Solicitations

Number Deadline
8745 - Stevens Street Assessment District - 2024
The work includes replacement of sanitary sewer main, replacement of sanitary laterals, and replacement and installation of storm sewer pipes and structures, excavation, base preparation, curb and gutter, driveway aprons, sidewalk replacement, asphalt pavement, pavement marking and signing.
05/23/2024 07:00 PM UTC
8709 Doncaster Beverly Danbury Reconstruction Assessment District - 2024
The work includes replacement of sanitary sewer main, replacement of sanitary laterals, replacement of water main, replacement of storm sewer main and storm sewer structures, terrace rain gardens, excavation, base preparation, curb and gutter, driveway aprons, sidewalk, and asphalt pavement.
05/23/2024 07:00 PM UTC
9487 - CIPP UV Lining Rehabilitation of Sewers Phase 1 - 2024
The work includes the trenchless rehabilitation of approximately 14,973 linear feet of sanitary sewer pipelines ranging in size from 8” to 15” diameter using an Ultraviolet light cure CIPP system. This contract shall also include the trenchless rehabilitation of approximately 860 linear feet of corrugated metal pipe (CMP) storm sewer pipelines with sizes of 21” diameter circular and 18”x24” elliptical using a thermal cure CIPP system.
05/09/2024 07:00 PM UTC
8740 - Hermina St & Union St Reconstruction Assessment District
The work includes the removal and replacement of the following: sanitary sewer main and laterals, storm sewer pipes and structures, asphalt pavement and roadway gravel base, concrete curb & gutter, concrete driveway aprons, and concrete sidewalk as needed.
05/09/2024 07:00 PM UTC
9497 - Streets West Facility HVAC and Lighting Upgrade
The work includes replacement of garage ventilation system with new make-up air unit and exhaust fan system. Lighting will be replaced in all garage and shop areas.
04/25/2024 07:00 PM UTC
9525 - 2024 Sport Court Resurfacing
The work includes resurfacing and/or power washing existing basketball and tennis courts including crack sealing, seal coating, and court line painting at three (3) City of Madison project sites including Goodman, Huegel and Quann Parks.
04/25/2024 07:00 PM UTC
9526 - 2024 Rennebohm Park East Tennis Courts
The work includes installing asphalt pavement, including base course for asphalt path and pickleball/tennis courts, installing footings/bases and electrical supply for the court lighting system, installing fencing, gates, net posts, net tie downs and sport court finishing and striping to construct a three (3) court (pickleball and tennis) complex at Rennebohm Park.
04/25/2024 07:00 PM UTC
8317 - Blue Harvest Lane, Feather Edge Drive, & Soaring Sky Run Assessment District - 2023
The work under this contract shall include, but is not limited to, installation sanitary sewer main, laterals, water main and services, storm sewer structures and pipes, culverts, earthwork, base preparation, curb and gutter, asphalt pavement, sidewalk, shared-use path, driveway aprons, pavement marking, and restoration.
04/25/2024 07:00 PM UTC
8695 - Safe Streets Madison 2024
The work includes installing traffic calming measures, pedestrian improvements and intersection updates at various locations in the City. This generally includes the installation of traffic calming islands, speed humps, sidewalk, curb and gutter, and pavement markings.
04/11/2024 07:00 PM UTC
8735 - E. Wilson St. and E. Doty St. Reconstruction Assessment District - 2023
The work includes replacement and installation of sanitary sewer pipes and structures, water main, and storm sewer pipes and structures, and replacement of street infrastructure including curb and gutter, pavement, sidewalk, driveway aprons, and installation of new bicycle facilities, underground terrace and sidewalk support systems, pavement marking, and signing.
04/04/2024 07:00 PM UTC
121 - 130 of 1107 Solicitations