| Name * | Description | |
|---|---|---|
| Number | Deadline |
|---|---|
|
OSM 61(0807,6967)101.1
Abandoned Mine Reclamation Project
Smith Corners
Clinton Township, Venango County
Estimated Amount: $500,000 to $1,000,000
Term: 180 calendar days
Bid Bond Required
Principal Items of Work and Approximate Quantities:
Implementation of the Erosion and Sediment Pollution Control Plan – Rock Construction
Entrance, 3 EACH
Implementation of the Erosion and Sediment Pollution Control Plan – Compost Filter Sock (32”
Diameter), 4,650 L.F.
Implementation of the Erosion and Sediment Pollution Control Plan – Weighted Sediment Filter
Tube,145 L.F.
Clearing and Grubbing, 23.1 ACRE
Grading – Grading Area 1, 24,450 C.Y.
Grading – Grading Area 2, 141,209 C.Y.
Grading – Grading Area 3, 13,626 C.Y.
Grading – Ripping, 15.2 ACRE
Planting – Planting Preparation, 23.1 ACRE
Planting – Tree Seedlings, 10,345 EACH
Planting – Grass Seed, 240 LB.
Subsurface Drain, 1,990 L.F.
Permanent Channel Excavation, 208 C.Y.
Erosion Matting, 767 S.Y.
Selective Grading, 200 ACRE
Implementation of the Traffic Control Plan, 1 L.S.
| 06/04/2026 06:00 PM UTC |
|
OSM 17(6425)101.1
Abandoned Mine Reclamation Project
Keewaydin
Covington and Karthaus Townships, Clearfield County
Estimated Amount: $1,000,000-$5,000,000
Term: 360 calendar days
Bid Bond Required
Principal Items of Work and Approximate Quantities:
Implementation of the Erosion and Sediment Pollution Control Plan - Rock Construction Entrance, 1 EACH
Implementation of the Erosion and Sediment Pollution Control Plan - Compost Filter Sock (24” Diameter), 2,580 L.F.
Implementation of the Erosion and Sediment Pollution Control Plan - Compost Filter Sock (32” Diameter), 4,370 L.F.
Clearing and Grubbing, 20 ACRE
Demolition, Removal and Disposal of Buildings and Equipment, 1 L.S.
Dewatering and Diversion and Care of Water, 1 L.S.
Stream Crossings - Stream Crossing 1 - Rock Ford, 200 TON
Stream Crossings - Stream Crossing 2 - 60" RCEP, 50 L.F.
Stream Crossings - Stream Crossing 2 - R-6 Rock, 50 S.Y.
Stream Crossings - Stream Crossing 2 - 2A Aggregate, 90 C.Y.
Stream Crossings - Stream Crossing 3 - 72" RCEP, 150 L.F.
Stream Crossings - Stream Crossing 3 - R-6 Rock, 180 S.Y.
Stream Crossings - Stream Crossing 3 - 2A Aggregate, 230 C.Y.
Special Handling of Refuse Material - Baghouse Lime, 2,700 TON
Special Handling of Refuse Material - Placement of Refuse Mixture, 42,420 C.Y.
Grading – Grading, 70,000 C.Y.
Grading – Ripping, 10 ACRE
Selective Grading, 10 ACRE
Access Road, 2,600 L.F.
Planting/Seeding - Planting Preparation, 20 ACRE
Planting/Seeding - Tree Seedlings, 6,800 EACH
| 06/04/2026 06:00 PM UTC |
|
OOGM FS26-3
Cleaning Out and Plugging One (1) Abandoned Gas Well
Moon Township, Allegheny County
Estimated Amount: $100,000-$200,000 (Small Business Only)
Term: 365 calendar days
Bid Bond Required
Principal Items of Work and Approximate Quantities:
Clean out and plug one (1) abandoned gas well, estimated to be approximately 2000’ feet in depth, to Department specifications.
Prepare and restore well site
Mobilize and demobilize plugging equipment.
MANDATORY Pre-Bid Conference will be held on: May 13, 2026, at 10:00 a.m.
Department representatives will meet contractors at:
Robert Morris University
Parking Area on Colonial Way (Next to Baseball Field)
40.523194, -80.210583
FAILURE TO ATTEND THE PRE-BID MEETING WILL BE CAUSE FOR REJECTION OF THE BID.
| 06/18/2026 06:00 PM UTC |
|
OSM 05(2002,7054)101.1
Abandoned Mine Reclamation Project
Kimber Mountain NW
Broad Top Township, Bedford County
Estimated Amount: Greater than $5,000,000
Term: 730 calendar days
Bid Bond Required
Principal Items of Work and Approximate Quantities:
Implementation of the Erosion and Sediment Pollution Control Plan – Rock Construction Entrance, 4 EACH
Implementation of the Erosion and Sediment Pollution Control Plan – Compost Filter Sock (32” Diameter), 17,674 L.F.
Implementation of the Erosion and Sediment Pollution Control Plan – Riprap Apron, 89 S.Y.
Clearing and Grubbing – Grading Area 1, 79.0 ACRE
Clearing and Grubbing – Grading Area 2, 17.2 ACRE
Clearing and Grubbing – Grading Area 3, 7.4 ACRE
Clearing and Grubbing – Grading Area 4, 1.9 ACRE
Clearing and Grubbing – Grading Area 5, 35.6 ACRE
Clearing and Grubbing – Grading Area 6, 7.5 ACRE
Access Road – New Road Construction, 1,826 L.F.
Access Road – Install Two-Inch (2”) PennDOT 2A on all roads at end of project, 2,229 TON
Subsurface Drain, 3,844 L.F.
Dewatering Impoundments, 1 L.S.
Grading – Grading Area 1, 1,133,874 C.Y.
Grading – Grading Area 2, 114,232 C.Y.
Grading – Grading Area 3, 33,166 C.Y.
Grading – Grading Area 4, 8,618 C.Y.
Grading – Grading Area 5, 490,907 C.Y.
Grading – Grading Area 6, 68,351 C.Y.
Permanent Channel Excavation, 360 C.Y.
Rock Lining, 2,436 S.Y.
Seeding – Seed Bed Preparation, 148.6 ACRE
Seeding – Seed, 6,241 LB.
Woodrat Mitigation Structures, 9 EACH
MANDATORY Pre-Bid Conference will be held on: June 1, 2026, at 9:00 a.m.
Department representatives will meet contractors at: 40°07'23.19"N 78°14'20.28"W
FAILURE TO ATTEND THE PRE-BID MEETING WILL BE CAUSE FOR REJECTION OF THE BID.
| 06/18/2026 06:00 PM UTC |
| Number | Deadline |
|---|---|
|
OSM 03(1109)101.1
Abandoned Mine Reclamation Project, Brownstown East, Kiskiminetas Township, Armstrong County
Estimated Amount: $100,000 to $200,000
Small Business Only
Term: 180 Calendar Days
Bid Bond Required
Principal Items of Work and Approximate Quantities:
Mobilization and Demobilization, 1 L.S.
Gas Facility Protection, 1 L.S.
Preparation and Implementation of the Erosion and Sediment Pollution Control Plan, 1 L.S.
Clearing and Grubbing, 1 L.S.
Demolition, Removal and Disposal of Mine Structures, 1 L.S.
Sealing Mine Entries, 5 Each
Sealing Mine Entries – Eight-Inch (8”) Diameter SDR-35 PVC Pipe, 200 L.F.
Seeding, 1 L.S.
| 03/10/2022 07:00 PM UTC |
|
OOGM 21-1
Cleaning Out and Plugging Seven (7) Orphan Oil and Gas Wells, Mead Township, Warren County, PA
ON BID FORM, PLEASE DISREGARD THE FOLLOWING:
**REQUIRED FOR CONTRACTS ESTIMATED OVER $50,000...
Mandatory Pre-Bid Conference will be held on January 20, 2022 at 9am. Location: Chapman State Park, 4790 Chapman Dam Road, Clarendon, PA 16313-2830
(5 miles southwest of Clarendon, PA)
Parking Lot and/or Pavilion 1 (just past the spillway)
Estimated Amount: $100,000 to $200,000 (Small Business Only)
Term: 180 Calendar Days
Bid Bond Not Required
Principal Items of Work and Approximate Quantities:
Clean-out and plug seven (7) orphan oil and gas wells, estimated to be up to 2,000 feet in depth, to Department specifications.
Prepare and restore well sites.
Mobilize and demobilize plugging equipment.
| 02/24/2022 07:00 PM UTC |
|
AMD 32(2722)102.1 (DGS 193-38)
Abandoned Mine Reclamation Project
Blacklick Creek Treatment Facility (Wehrum)
Blacklick Township, Cambria County and
Buffington and East Wheatfield Townships, Indiana County
Estimated Amount: Greater than $5,000,000
Term: 1,000 calendar days
Bid Bond Required
Principal Items of Work and Approximate Quantities:
(See page 1 of Bid Information.)
MANDATORY PRE-BID MEETING will be held on
December 15, 2021 at 10:00 a.m.
Department representatives will meet contractors at:
DEP Cambria Office
Bureau of Abandoned Mine Reclamation
1st Floor, Room 1A & 1B
286 Industrial Park Road
Ebensburg, PA 15931
FAILURE TO ATTEND THE PRE-BID MEETING WILL BE CAUSE FOR REJECTION OF THE BID.
*No Small Diverse Business Goals were determined for this project.
| 01/27/2022 07:00 PM UTC |
|
OSM 17(7050)101.1
Abandoned Mine Reclamation Project
Muddy Run East
Gulich Township, Clearfield County
Estimated Amount: $200,000 to $299,999 (Small Business Only)
Term: 210 calendar days
Bid Bond Required
Principal Items of Work and Approximate Quantities:
Dewatering Impoundments, 1 L.S.
Clearing and Grubbing, 1 L.S.
Subsurface Drains with Cleanouts, 1,750 L.F.
Grading, 78,400 C.Y.
Rock Lining, 244 S.Y.
Seeding, 13.2 Acre
| 12/02/2021 07:00 PM UTC |
|
AMD 54(4124)108.1
Acid Mine Drainage Abatement Project
Rausch Creek Treatment Plant Lime Tank Replacement
Hegins Township, Schuylkill County
Estimated Amount: $300,000 to $500,000
Term: 180 Calendar Days
Bid Bond Required
Principle Items of Work:
Temporary Lime Supply - 1 L.S.
Removal of Existing Lime Storage Tank - 1 L.S.
Installation of New Lime Storage Tank -1 L.S.
Anchoring System - L.S.
No Mandatory Pre-Bid Meeting has been scheduled.
| 12/02/2021 07:00 PM UTC |
|
OOGM 20-4
Cleaning Out and Plugging One Abandoned Well in Stewardson Township, Potter County.
Mandatory Pre-Bid Meeting to be held on Tuesday, October 26, 2021 at 10:00 A.M. at the pavilion in Ole Bull State Park.
Estimated amount of Project: 200,000 to 299,999 (Small Business Only)
Term: 90 calendar days.
Bid Bond NOT Required.
Principal Items of Work and Approximate Quantities:
Clean-out and plug one (1) abandoned gas well, estimated to be 7,000 feet in depth, to Department specifications.
Prepare and restore well sites.
Mobilize and demobilize plugging equipment.
| 11/18/2021 07:00 PM UTC |
|
OSM 40(4241)101.1
Abandoned Mine Reclamation Project
46 Birch Ave. Nanticoke
City of Nanticoke, Luzerne County
Estimated Amount $100,000 to $200,000 (Small Business Only)
Term: 60 Calendar Days
Bid Bond is Required
Principal Items of Work and Approximate Quantities:
Drilling Boreholes – Vertical Air Rotary Drilling to Accommodate Six-Inch (6”) Casing, 175 L.F.
Drilling Boreholes – Angular Air Rotary Drilling to Accommodate Six-Inch (6”) Casing, 40 L.F
Furnishing and Installing Casing Pipe, 120 L.F.
Fill Material Injection – Flowable Fill Material Through Borehole, 100 C.Y.
Fill Material Injection – Concrete Fill Material Through Borehole, 750 C.Y.
Sealing Boreholes, 5 EACH
| 11/18/2021 07:00 PM UTC |
|
OSM 16(1041)101.1
Abandoned Mine Reclamation Project
Manor Church Southeast
Paint Township, Clarion County
Estimated Amount: $300,000-$500,000
NO GOALS DETERMINED.
PLEASE DISREGARD ATTACHMENT A.
Term: 300 calendar days
Bid Bond Required
Principal Items of Work and Approximate Quantities:
Dewatering Impoundments, 1 L.S.
Clearing and Grubbing, 1 L.S.
Subsurface Drains with Cleanouts, 1,569 L.F.
Grading, 120,750 C.Y.
Erosion Matting, 340 S.Y.
Rock Lining, 36 S.Y.
Twelve-Inch (12”) Mine Drain Pipe, 330 L.F.
Twenty-Four Inch (24”) Bat Gate Pipe - Corrugated Smooth Interior Polyethylene Pipe, 220 L.F.
Twenty-Four Inch (24”) Bat Gate Pipe - Corrugated Metal Pipe, 10 L.F.
Steel Bat Gate Attachment to Bat Gate Pipe, 1 EACH
AASHTO No. 1 Aggregate Backfill, 15.5 TON
Seeding, 23.3 ACRE
Tree Planting, 2,004 TREE
No Mandatory Pre-Bid Meeting.
| 10/28/2021 06:00 PM UTC |
|
OSM 17(1192,7157)101.1
Abandoned Mine Reclamation Project
Eden East Water Main Extension
Goshen Township, Clearfield County
Estimated Amount: $1,000,000 to $5,000,000
Term: 365 calendar days
Bid Bond Required
Principal Items of Work and Approximate Quantities:
Site Preparation and Restoration – 1 L.S.
Six Inch (6") PVC Pipe or HDPE Pipe Including Fittings – 53,025 L.F.
Six-Inch (6") Gate Valve – 57 Each
Two-Inch (2") PVC Pipe or HDPE Pipe Including Fittings – 10,900 L.F.
2A Stone – 30,100 C.Y.
Three-Quarter Inch (3/4") Service – 91 Each
Three-Quarter Inch (3/4") Polyethylene Pipe – 3,500 L.F.
Three-Quarter Inch (3/4”) Automatic Air Release Valve – 11 Each
Two-Inch (2”) Blow-off Assembly – 15 Each
Pressure-Reducing Vaults – 2 Each
Glass Fused to Steel Bolted-Steel Water Storage Tank Including Foundation and Vault – 1 L.S.
Packaged Water Booster Pumping Station Complete – 1 L.S.
*NO GOALS WERE DETERMINED FOR THIS PROJECT. PLEASE DISREGARD SPECIAL REQUIREMENT NO. 1 ON PAGE SR-1, AND ALSO DISREGARD ATTACHMENT A FOR THIS PROJECT.
| 10/21/2021 06:00 PM UTC |
|
OSM 16(3571)101.1
Abandoned Mine Reclamation Project
Arthurs Southeast
Paint Township, Clarion County
Estimated Amount: $100,000 to $200,000 (Small Business Only)
Term: 210 calendar days
Bid Bond Required
Principal Items of Work and Approximate Quantities:
Clearing and Grubbing, 1 L.S.
Grading, 50,300 C.Y.
Seeding, 7.7 Acre
Tree Planting, 1,480 Tree
| 09/09/2021 06:00 PM UTC |
You have successfully created your Digital ID. It has been installed to your browser.
We recommend that you also download a backup of your Digital ID and save it securely to an external storage location, as this file must be installed again if you intend to use a different browser or computer for bidding, document signing, and solicitation management.
Learn more about managing your Digital ID.Click Install Backup ID to use your Digital ID in this location.
If you don't have a copy of your backup ID, but you have access to the computer and browser where it was first created, you can still create a backup ID to install to this location. For help, see how to back up your Digital ID.
If you don't have access to the original computer and browser, you can create a new Digital ID below.