City of Lake Charles
326 Pujo Street, Lake Charles, LA 70601
(337) 491-1263
326 Pujo Street, Lake Charles, LA 70601
(337) 491-1263
| Name * | Description | |
|---|---|---|
| Number | Deadline |
|---|---|
|
DR002
City of Lake Charles, Louisiana
Lake Charles Public Works New Facility Phase 2
DR002
Scope of Project
Build a variety of new buildings on an existing partially developed site. Project to include parking, generators, underground drainage, drainage swales and detention areas, enclosed conditioned buildings, open air pavilions, vehicle canopies, a new fuel station, and other work as noted in plans and specifications.
| 02/16/2026 08:45 PM UTC |
|
LCR 401
City of Lake Charles, Louisiana
Lock Park Inclusive Playground
LCR 401
CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents for the LCR 401 Lock Park Inclusive Playground. The Work includes, but is not limited to:
PROJECT SUMMARY:
• The scope of work that is considered base bid includes:
o Necessary earthwork, grading, tree protection, and utility adjustments to accommodate the proposed playground and parking;
o Demolition of the two (2) stall concrete parking lot off 6th Street, the central pedestrian promenade connecting 6th Street to 7th Street, select removal of concrete paths to accommodate drainage and curb ramps, and the removal of select trees;
o Installation of vehicular rated concrete paving for a parking lot and entry drive, custom playground components, poured-in-place safety surfacing on a gravel and concrete base, engineered wood fiber safety surfacing, two (2) pre-engineered shade structures, concrete curbs and pedestrian paths, subsurface drainage, site lighting, playground fencing, planting, and an irrigation system.
• The scope of work that is considered alternates includes:
o Alternate No. 1: Add vehicular rated paving and curbs east of proposed drive aisle.
o Alternate No. 2: Add planting and irrigation in parking islands and in front of pavilion.
| 02/16/2026 08:45 PM UTC |
|
2026-12
Millennium Park Fall Surface Replacement
In accordance with the specifications, it is the intent of this formal invitation to receive bids from qualified bidders for Materials, Supplies and Labor for the removal of existing poured-in-place rubber surfacing, preparation of the underlying concrete slab, and installation of a synthetic turf playground surfacing system with an impact attenuation pad and silica sand infill for Millennium Park, located on the grounds of the Bord du Lac Park, adjacent to the Lake Charles Event Center.
All work shall be performed in a clean, safe, and workmanlike manner in accordance with manufacturer specifications and ASTM standards for playground surfacing safety and accessibility.
| 03/03/2026 08:45 PM UTC |
|
Project No. 2025-749 Capital Project No. 3309
PROJECT NO. 2025-749
CAPITAL PROJECT NO. 3309
HAM REID ROAD WATERLINE EXTENSION-
ELLIOTT RD. TO BIG LAKE RD.
CITY OF LAKE CHARLES, LA
SCOPE OF WORK:
The scope of work includes the installation of new 12” diameter waterline along the north side of Ham Reid Road between Elliot Road and Big Lake Highway (LA 384). The scope also includes the relocation of the existing 12” diameter water line at the intersection of La 384 and Graywood Parkway in anticipation of a new round-a-bout at this location.
| 03/03/2026 08:45 PM UTC |
| Number | Deadline |
|---|---|
|
CP 3338
City of Lake Charles, Louisiana
2019 Sidewalk Construction
CP 3338
The installation of a six-foot (6’) sidewalk along the west side of nelson road between Evergreen at River Oaks Apartments driveway and W. Mcneese Street, the installation of a five-foot (5’) sidewalk on the west side of Canal Street between W. Mcneese Street and W. Sale Road, the installation of a five-foot (5’) sidewalk along the south side of Madeline Street between Common Street and Kirkman Street, the installation of a four- to five-foot (4’-5’) sidewalk along the south side of Illinois street between Brentwood Avenue and E. Walton Street, and the removal and replacement of existing concrete curbing and a five-foot (5’) sidewalk along the east and west sides of Bilbo Street between Clarence Street and Iris Street. It also includes the installation and adjustment of subsurface drainage systems along Nelson Road and Canal Street, the removal and installation of driveways impacted by sidewalk placement, and the installation of a retaining wall along the sidewalk located on the east side of Bilbo Street.
| 03/15/2022 07:45 PM UTC |
|
Project No. 2021-711 Capital Project No. 3372
Project No. 2021-711
Capital Project No. 3372
Louisiana Avenue – South of McNeese – Drainage Improvements
City of Lake Charles, LA
The general scope of work for Project 2021-711, Capital Project No. 3372 is the installation of new underground drainage system to better serve Louisiana Avenue south of McNeese Street. This new system will tie into McNeese Street, run south along the east property line of F.K. White Middle School, and then turn east along the south property line of the Entergy Substation. The system will cross to the east side of Louisiana Avenue at this location. Additionally, this underground system will extend south in the existing west roadside ditch of Louisiana Avenue approximately 650 feet. This new underground system will consist of new drainage inlets and pipe ranging from 15” to 48” in diameter, as well the associated pavement work.
| 03/15/2022 07:45 PM UTC |
|
CP 3339
City of Lake Charles, Louisiana
Lakefront Parking Garage – Phase II
CP 3339
1. The Work includes repairs to existing parking garage structure.
a. Demolition and removal CMU walls and metal wall panels.
b. Replacement of existing electrical equipment, new lighting & specialty lighting.
c. New elevator core and storefront systems for elevator lobbies at each level.
d. New curtain wall system.
e. New exterior metal stair units.
f. Repairs to existing buildings including roofing, fascia, soffit, pre-finished metal
siding, framing, sheathing, flooring, re-painting etc.
g. New retaining wall foundations and waterproofing.
h. Fascade replacement of pre-finished metal wall panels.
i. Re-stripping of parking area & misc. painting.
| 02/01/2022 08:45 PM UTC |
|
HL-69
City of Lake Charles, Louisiana
Public Works Admin Building Demo
HL-69
Remove existing 2-story building, foundation, paving, and all related components in their entirety. Project includes asbestos abatement of hazardous material in building.
| 02/01/2022 08:45 PM UTC |
|
Capital Project No. HL-16
Project No. 2021-716
Capital Project No. HL-16
Bord du Lac Drive – Fishing Piers
City of Lake Charles, LA
The general scope of work is as follows:
A. Pier/Shelter A:
Pier A was severely damaged during the 2020 hurricane season and is considered a total loss. The shelter area of this pier is partially submerged in the Lake.
The general scope of work for Pier A includes the following general items:
• Secure access to the work zone prior to work.
• Complete removal and disposal of Pier A, including but limited to the timber deck, handrails, lights, light poles and conduits, pilings, bracing, framing, shelter, benches, tables, steel framing units, cross bracing, and timber pilings. The removed light poles shall be salvaged for possible re-use.
• The electrical circuit shall be properly terminated at the on-shore pull box.
• Riprap (Class 30lb.) will be placed along the bank to backfill the void left by the removal of this pier and walkway. The finished surface of the new riprap shall match the adjoining areas that have been recently improved with riprap. Additional riprap shall be placed at the very end of the concrete walk to provide a visual barrier to the former pier access.
B. Pier/Shelter B:
Pier B was moderately damaged during the 2020 hurricane season and is considered a partial loss. While the structure can be salvaged, some portions will require adjustment and repair.
The general scope of repair includes the following general items:
• Secure access to the work zone prior to work.
• Replacement of lost or damaged timber deck in areas damaged by the hurricane with new 0.40 ACQ treated lumber to match exist. Existing deck timber is treated pine lumber (nominal 3 x 12 dimensions) measuring approximately 11¼ inch wide by 2½ inch thick by length required. The new decking shall be secured in place with 3/8” galvanized carriage bolts and nuts. A center line beam was added to the deck that is not identified on the available reference Lakefront Boardwalk Project 9412 construction plans. This beam may require widening of the holes to install the 3/8-inch galvanized carriage bolts.
• Elevation Adjustment of two deck support framing units, one next to the concrete landing, and one at the end of the branch walkway to the shelter. It is the intent to salvage and re-use the existing galvanized deck framing units. The deck section next to the concrete landing is not level with the landing and creates a step hazard. This first framing unit shall be lifted or removed to access the piling at this location. The timber decking for this first framing unit will be removed and replaced with new decking material. The piling adjacent to the concrete landing shall be trimmed so that the restored timber deck matches the concrete landing in elevation. The frame unit at the end of the branch walkway over the water has dropped down primarily in one corner. This end framing unit shall be lifted or removed to access the piling at this location. The timber decking for this end framing unit will be removed and replaced with new decking material. This corner shall be lifted, and a treated filler block shall be securely installed to raise this corner and correct this deck alignment to restore a level walkway. This scope includes any handrail removal and re-installation as needed to facilitate this work. All frame units shall be inspected, and missing bolts replaced or tightened.
• Removal and replacement of all lighting, poles, conduits, wiring complete including connection to electrical circuit on shore. The poles shall be salvaged for re-use. The better of the salvaged poles shall be repainted black and re-installed with new fixture similar to the recent electrical work along the boardwalk. New fixtures shall be installed in the shelter.
• Re-securing all the framing units to the timber piles with new galvanized lag bolts. The new lag bolts shall be 5/8” diameter – 8 inches long. The existing holes may need to be widened to fit the new bolts. Two (2) bolts are required per pile. Any missing or loose bolts or fasteners shall be replaced or tightened as appropriate.
• Gaps observed in the handrail segments shall be corrected.
• The entire walkway shall be pressure washed. The picnic table and benches shall be re-surfaced (sanding). The galvanized support members for this shelter shall be repainted with a compatible galvanized paint.
C. Pier/Shelter C:
Pier C was severely damaged during the 2020 hurricane season and is considered a total loss. The shelter area of this pier is partially submerged in the Lake.
The general scope of work for Pier C includes the following general items:
• Secure access to the work zone prior to work.
• Complete removal and disposal of Pier C, including the timber deck, handrails, lights, light poles and conduits, bracing, framing, shelter, benches, tables, steel framing units, cross bracing, and timber pilings. The removed light poles shall be salvaged for possible re-use.
• The electrical circuit shall be properly terminated at the on-shore pull box.
• Riprap (class 30 lb.) will be placed along the bank to backfill the void left by the removal of this pier and walkway. The finished surface of the new riprap shall match the adjoining areas that have been recently improved with riprap. Additional riprap shall be placed at the very end of the concrete walk to provide a visual barrier to the former pier access.
D. Walkways:
1. Veteran’s Memorial Walkway:
The Veteran’s Memorial Walkway was severely damaged during the 2020 hurricane season and is a total loss. This pier was lifted off its support piles and washed ashore. This timber walkway will be completely removed (onshore and offshore) and not restored under this program.
The general scope of repair includes the following general items:
• Secure access to the work zone prior to work.
• Complete removal and disposal of remaining timber deck, handrail, pilings, bracing, framing, and lighting, both on shore and offshore. Onshore pilings may be completely removed or cut off a minimum of 2 feet below existing grade at the contractor’s option. All pilings in the water shall be completely removed. Pilings adjacent to the concrete landing shall be completely removed or cut off a minimum of 2 feet below existing riprap grade.
• Site fill to restore areas impacted by removal of this timber walkway structure on shore shall be placed. Site fill to consist of topsoil and the site shall be leveled to match adjoining grade. Upon completion, the area shall be hydroseeded. Additional riprap (Class 30lb.) shall be added to supplement the existing around the concrete landing as directed by the engineer.
2. PPG Walkway:
The PPG walkway is located Northeasterly of the PPG fountain and re-connects to the shoreline just south of Pier B. This walkway had moderate damage during the 2020 hurricane season and is currently closed to pedestrian traffic.
The general scope of repair includes the following general items:
• Secure access to the work zone prior to work.
• Replacement of missing or damaged deck material as identified and re-securing loose decking to the existing galvanized frame. Replacement timber deck shall be with new 0.40 ACQ treated lumber to match exist. Existing deck timber is treated pine lumber (nominal 3 x 12 dimensions) measuring approximately 11¼ inch wide by 2½ inch thick by length required. The new decking shall be secured in place with 3/8” galvanized carriage bolts and nuts. A center line beam was added to the deck that is not identified on the available reference Lakefront Boardwalk Project 9412 construction plans. This beam may require widening of the holes to install the 3/8-inch galvanized carriage bolts. The entire walkway shall be cleaned and pressure washed upon completion of the work. All frame units shall be inspected, and missing bolts replaced or tightened.
• Re-securing all the framing units to the timber piles with new galvanized lag bolts. The new lag bolts shall be 5/8” diameter – 8 inches long. The existing holes may need to be widened to fit the new bolts. Two (2) bolts are required per pile. Any missing or loose bolts or fasteners shall be replaced or tightened as appropriate.
• Removal and replacement of all lighting, poles, conduits, wiring complete including connection to electrical circuit on shore. The better of the salvaged poles shall be repainted black and re-installed with new fixtures similar to the recent electrical work along the boardwalk.
| 02/01/2022 08:45 PM UTC |
|
Various City Park Repairs - Phase I
City of Lake Charles, Louisiana
Hurricane Laura Storm Repairs – Various City Park Repairs – Phase I
HL – 05, 12, 20, 120, 139, 140, 142, 143, 144, 145, 146, 147
1. The Work includes repairs to multiple existing park facilities:
a. Repair existing bleacher cover structures.
b. Replace damaged bleachers.
a. Chain-link fencing repair/replacement.
b. Repairs to lighting and mechanical systems.
c. Repairs to existing buildings including roofing, fascia, soffit, siding, framing, sheathing,
flooring, gypsum board, painting etc.
d. Replacement of open air pavilion.
e. Repairs to wood fencing.
f. Repair/replace exterior and field lighting.
g. Conversion of tennis court to basketball court.
| 01/18/2022 08:45 PM UTC |
|
Project No. 2021-718 Capital Project No. 3276
Project No. 2021-718
Capital Project No. 3276
College Heights Detention Pond Rehabilitation
City of Lake Charles, LA
The general scope of work is the restoration of the existing storm water detention pond serving College Heights Subdivision Phase One to its original volume. The scope includes clearing of the vegetation, removal of the siltation to plan grade, reshaping of the side slopes, placement of an erosion control blanket along the side slopes, concrete block erosion control mat, and placement of a vinyl retaining wall along the East side of Lots 28 and 56 College Heights Sub Phase 1, and hydroseeding.
| 01/04/2022 08:45 PM UTC |
|
Repair Project HL-SOV-029
City of Lake Charles
WWTP B/C Tank Debris Removal and Disposal Project
Hurricane Laura (DR-4559-LA) Recovery Program
Repair Project HL-SOV-029
Scope of Services:
Removal of storm blown debris from open top wastewater tanks at WWTP B/C, in response to damage incurred as a result of Hurricane Laura (DR-4559-LA). This Work shall include the following:
A. GENERAL
1. Sludge material in tanks listed below to be dewatered, hauled, and disposed of at an approved landfill.
2. The landfilled product shall have a minimum solids content of 16%.
3. It shall be the contractor’s responsibility to provide means and methods for the completion of all specified criteria listed herein.
B. WWTP B/C
1. Remove and dispose of debris in Digester No. 1 (SOV 29).
2. Remove and dispose of debris in Aeration Basin No. 1 (SOV 29.A.1).
| 12/14/2021 08:45 PM UTC |
|
CP 3316
City of Lake Charles, Louisiana
Project Name: Mallard Golf Club Lake Charles
Clubhouse & Pro Shop
Capital Project Number: CP3316
New 7000 SF Clubhouse facility will include Pro Shop, Offices, Restrooms, Dinning/Bar and Kitchen
| 11/30/2021 08:45 PM UTC |
|
Capital Project Number CP3250
CITY OF LAKE CHARLES, LOUISIANA
KIRKMAN AND OPELOUSAS
MODIFICATIONS AND RECONSTRUCTION
CAPITAL PROJECT NUMBER CP3250
Scope of Services:
The City of Lake Charles desires to provide roadway repairs to the existing Kirman Street
and Opelousas Street intersection. Repairs to the existing roadway shall consist of the
removal of roadway pavement, damaged and/or non-ADA compliant sidewalk pavement,
waterline and sewer line relocation/replacement, and drainage improvements required to
reconstruct this damaged intersection.
| 11/30/2021 08:45 PM UTC |
You have successfully created your Digital ID. It has been installed to your browser.
We recommend that you also download a backup of your Digital ID and save it securely to an external storage location, as this file must be installed again if you intend to use a different browser or computer for bidding, document signing, and solicitation management.
Learn more about managing your Digital ID.Click Install Backup ID to use your Digital ID in this location.
If you don't have a copy of your backup ID, but you have access to the computer and browser where it was first created, you can still create a backup ID to install to this location. For help, see how to back up your Digital ID.
If you don't have access to the original computer and browser, you can create a new Digital ID below.