OSU-210742, Arps - Masonry & Parapet
OSU Columbus Campus: Masonry wall repairs and low-slope roof replacement for Arps Hall.
04/06/2026 06:00 PM UTC
OSU-250040 Fire Systems Renovations - FY25-26
Kuhn Honors and Scholars House, Graves Hall, Tzagournis Medical Research Facility
04/08/2026 06:00 PM UTC
OSU-255631, Morehouse Medical Plaza - Concourse - Medical Gas Enclosure and Upgrade
This project entails the addition of a new dedicated medical gas storage enclosure at the facility to safely house increased medical oxygen cylinder capacity in compliance with NFPA 99 standards, featuring secure noncombustible construction, proper ventilation, cylinder restraints, and required safety signage. The scope includes installation of additional medical oxygen drops in targeted patient care areas via new copper piping, zone valves, and alarm integrations, along with the strategic relocation of existing medical gas equipment to optimize accessibility, maintenance, and system redundancy. All work will involve phased implementation to minimize disruptions, full system purging, pressure testing, third party certification, and verification to ensure code-compliant, safe, and reliable medical gas delivery supporting current operations and future facility expansion.
04/10/2026 06:00 PM UTC
OSU-250039 Elevator Renovations - FY 25-26
Elevator Modernization and related architectural and MEP scopes of work at Pressey Hall on OSU’s Main Campus.
04/16/2026 06:02 PM UTC
OSU-230102 Roof Renewal FY23-24 BP 1
Work includes roof replacements on Agriculture Administration or “Ag Admin”, located at The Ohio State University Columbus Campus in Columbus, Ohio
04/23/2026 06:00 PM UTC
5 Solicitations

Closed Solicitations

Number Deadline
OSU-160319 Rhodes - Bronchoscopy Procedure Rooms
This project will renovate rooms S247 and S251 into bronchoscopy procedure rooms.
08/30/2018 05:30 PM UTC
OSU-160978 Fire Alarm Replacements Phase 2
The work consists of the removal and replacement of existing fire alarm systems in 6 buildings (Agricultural Engineering Building, Evans Lab, Mershon Auditorium, Newman and Wolfrom Laboratory, Parks Hall and Rightmire Hall) with new, addressable systems. Related work includes hazardous material abatement, patching and painting of walls at removed equipment, and limited ceiling replacement
08/30/2018 05:00 PM UTC
OSU-180221, Drackett Tower - Boiler Replacements
The Project consists of the replacement of 2 domestic water converters with gas-fired water heaters and replacement of 2 heating water boilers on the 13th and 14th Floors of Drackett Tower. The work also includes replacement of 2 domestic water storage tanks, 2 existing cooling towers, and 6 heating water expansion tanks. A new domestic hot water thermostatic mixing valve will be installed for scald protection. The work will be done in phases for minimum impact to building operation.
08/29/2018 06:00 PM UTC
OSU-180526 33 W 11th - Chiller Replacement
This project will install a new chiller on the roof
08/23/2018 05:00 PM UTC
OSU-170213 - Doan Exterior Brick Repair
This project will repair the exterior brick and steel lintels.
08/16/2018 05:30 PM UTC
OSU-180039, Ag Admin - Restroom Renovations
Main Campus: The renovation of approximately 1,676 SF of Restroom space in the Agricultural Administrative Building located at 2120 Fyffe Road, in Columbus, Ohio. The project scope includes rooms 027T, 031T, 038T, 038A, 040T, 100T, 102T and 103T. The new restroom renovations will reconfigure the rooms identified above to include Group and Family Restrooms, and a Wellness Room.
07/31/2018 06:00 PM UTC
OSU-150403
University Hospital - Relocate Surgical Pathology Phase II
07/18/2018 05:30 PM UTC
OSU-150572 Psychology - Envelope Repair
1835 Neil Avenue, Columbus Restore the original design intent of the exterior envelope of the Psychology Building by removing and reinstalling the existing Centria Insulated Metal Panel cladding. Prior to reinstalling, additional measures including, but not limited to, roofing termination repairs, firestopping repairs, and flashing and substrate modifications will be implemented to maintain the air and watertightness of the exterior envelope.
07/18/2018 05:00 PM UTC
OSU-170535, Mansfield - Molyet Village Comm Bldg
One story wood frame 7,583 SF community building located near Molyet Village on the Mansfield campus of The Ohio State University. The project scope includes adjacent site area improvements, foundation and framing and exterior envelope, mechanical, electrical, technology and plumbing systems, fire alarm and fire protection systems, casework, finishes.
07/11/2018 06:00 PM UTC
OSU-170533, Lincoln Tower 14th Floor Renovation (REBID)
Lincoln Tower 14th Floor Renovation REBID 1800 Cannon Drive, Columbus, OH 43210 Complete renovation of the 14th floor of Lincoln Tower.
06/29/2018 06:00 PM UTC